PCPL Kaveri - Malad West, Mumbai
- Builder
- Pranav Constructions Limited
- Construction
- Under Construction
- Completion
- Jul, 2028
- Properties
- Apartments
- RERA
- P51800076922
Description
E-Charging Point For E-Vehicles
PCPL Kaveri is a premium residential development project located in Kanchpada, Malad West, Mumbai. The project development offers spacious 1 , 2 and 3 BHK residential apartments ranging from 440 to 1110 sq. ft., spanning approximately 0.73 acres of land. The project features a single wing of G+17-21 storeys, efficient with practical layouts, natural light, ventilation, Vaastu-compliant planning and 74 units.Amenities:
- Fitness Centre
- Landscaped Garden Area
- Blooming Deck
- Multipurpose Lawn
- Open-Air Movie Lounge
- Yoga Area
- Indoor Games
- Toddlers’ Play Area
- Senior Citizen Deck
- Outdoor Seating Areas
- High-Tech Security System
- 24/7 Water Supply
- Power Backup
- Well-Designed Lobby
- Intercom Facilities
- CCTV Surveillance
- Solar Pv Panels
- E-Charging Point
Pranav Constructions Limited (often referred to as PCPL) is a Mumbai-based real estate developer known primarily for residential developments, especially in the Western Suburbs of Mumbai, such as Malad, Goregaon, Kandivali, Borivali, Andheri, Santacruz, Juhu and Vile Parle.
Highlights
- Fitness Centre
- Landscaped Garden Area
- Blooming Deck
- Multipurpose Lawn
- Open-Air Movie Lounge
- Yoga Area
- Indoor Games
- Toddlers’ Play Area
- Senior Citizen Deck
- Outdoor Seating Areas
- High-Tech Security System
- 24/7 Water Supply
- Power Backup
- Well-Designed Lobby
- Intercom Facilities
- CCTV Surveillance
- Solar PV Panels
- E-Charging Point
Configurations
| Type | Area | Possession | Price * |
|---|---|---|---|
| 1BHK Apartment | 440 SqFeet | Within 2 Years | ₹ 1.19 crore |
| 2BHK Apartment | 708 SqFeet | Within 2 Years | ₹ 2.52 crores |
| 3BHK Apartment | 1,110 SqFeet | Within 2 Years | ₹ 3.55 crores |
RERA
P51800076922 REDEVELOPMENT OF KAVERI CHSL Active 81% built
Confirmed with MahaRERA on 21 Sep 2026. Registered as "REDEVELOPMENT OF KAVERI CHSL".
- Promoter
- PRANAV CONSTRUCTIONS LIMITED
- Registered on
- 9 Jul 2024
- Proposed completion
- Jul 2028 (originally Mar 2028)
- Project type
- Residential / Group Housing
- Planning authority
- MCGM
- Address as filed
- MARVE ROAD (LINKING ROAD), MALAD WEST, Malad, Borivali, Mumbai Suburban, 400064
- Land area
- 2,958 sq m (31,836 sq ft)
- Sanctioned built-up area
- 9,981 sq m (107,442 sq ft)
- Buildings
- KAVERI WING A (22 floors) - 18 of 27 available; KAVERI WING B (22 floors) - 14 of 34 available
- Parking
- Open Space 41, Closed/Covered 2
| Building | Unit type | Carpet area | Units |
|---|---|---|---|
| KAVERI WING A | 2BHK | 66 sq m (705 sq ft) | 3 |
| KAVERI WING A | 2 BHK REHAB | 66 sq m (708 sq ft) | 9 |
| KAVERI WING A | 3BHK | 103 sq m (1,110 sq ft) | 11 |
| KAVERI WING A | 3 BHK REHAB | 103 sq m (1,110 sq ft) | 5 |
| KAVERI WING A | 2BHK | 66 sq m (708 sq ft) | 6 |
| KAVERI WING A | Shop | 49 sq m (524 sq ft) | 1 |
| KAVERI WING A | Shop | 213 sq m (2,297 sq ft) | 1 |
| KAVERI WING A | Shop | 152 sq m (1,634 sq ft) | 1 |
| KAVERI WING A | Shop | 115 sq m (1,234 sq ft) | 1 |
| KAVERI WING A | 1 BHK REHAB | 47 sq m (509 sq ft) | 10 |
| KAVERI WING A | 2BHK | 47 sq m (509 sq ft) | 4 |
| KAVERI WING B | 3 BHK REHAB | 99 sq m (1,069 sq ft) | 9 |
| KAVERI WING B | 2 BHK REHAB | 63 sq m (677 sq ft) | 9 |
| KAVERI WING B | 3BHK | 99 sq m (1,069 sq ft) | 8 |
| KAVERI WING B | Shop | 172 sq m (1,849 sq ft) | 1 |
| KAVERI WING B | Shop | 131 sq m (1,405 sq ft) | 1 |
| KAVERI WING B | 1BHK | 41 sq m (440 sq ft) | 1 |
| KAVERI WING B | 2BHK | 66 sq m (708 sq ft) | 1 |
| KAVERI WING B | 2BHK | 63 sq m (682 sq ft) | 5 |
| KAVERI WING B | 1 BHK REHAB | 41 sq m (440 sq ft) | 11 |
| KAVERI WING B | 1BHK | 43 sq m (460 sq ft) | 5 |
| KAVERI WING B | Shop | 322 sq m (3,467 sq ft) | 1 |
| KAVERI WING B | 2BHK | 63 sq m (677 sq ft) | 3 |
| KAVERI WING B | 2BHK | 63 sq m (681 sq ft) | 7 |
| KAVERI WING B | Shop | 310 sq m (3,336 sq ft) | 1 |
| KAVERI WING B | 2 BHK REHAB | 63 sq m (681 sq ft) | 7 |
| Quarterly return | Filed | Built | Units booked |
|---|---|---|---|
| Q2 FY 2024-2025 | not filed - in default | - | - |
| Q3 FY 2024-2025 | 23 Jun 2025 | - | - |
| Q4 FY 2024-2025 | 23 Jun 2025 | - | - |
| Q1 FY 2025-2026 | 1 Aug 2025 | - | - |
| Q2 FY 2025-2026 | 14 Feb 2026 | - | - |
| Q3 FY 2025-2026 | 14 Feb 2026 | - | - |
| Q4 FY 2025-2026 | 28 Apr 2026 | - | - |
| Q1 FY 2026-2027 | 12 Aug 2026 | - | - |
Construction progress as reported to the portal
KAVERI WING A
- Excavation: 100%
- Basement (if any): 0%
- Podiums (if any): 93%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 48%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 0%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
KAVERI WING B
- Excavation: 1001%
- Basement (if any): 0%
- Podiums (if any): 93%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 48%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 0%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
Common areas and facilities
- Water Supply: 0% - WORK TO BE INITIATED
- Sewerage (Chamber, Lines, Septic Tank , STP): 0% - WORK TO BE INITIATED
- Storm Water Drains: 0% - WORK TO BE INITIATED
- Landscaping & Tree Planting: 0% - WORK TO BE INITIATED
- Treatment And Disposal Of Sewage And Sullage Water: 0% - WORK TO BE INITIATED
- Solid Waste Management And Disposal: 0% - WORK TO BE INITIATED
- Water conservation /Rain water harvesting: 0% - WORK TO BE INITIATED
- Energy managemcnt: 0% - WORK TO BE INITIATED
- Fire protection and fire safety requirements: 0% - WORK TO BE INITIATED
- Electrical meter room, sub-station, receiving station: 0% - WORK TO BE INITIATED
- Aggregate area of recreational Open Space: 0% - WORK TO BE INITIATED
- Open Parking: 0% - WORK TO BE INITIATED
Reviews
Write a review
Be the first to write a review of PCPL Kaveri and become a Project expert!
- Post an informative review and get 1 additional basic property listing FREE of cost*.
- Your review will be displayed prominently on your property listing page and other pages on the website.
- For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of PCPL Kaveri
Enter some positive aspects of PCPL Kaveri
Cons:
Enter some negative aspects of PCPL Kaveri
Enter some negative aspects of PCPL Kaveri
Location
PCPL Kaveri, Kanchpada, Malad West, Mumbai - 400064 (Maharashtra)
Nearby
-
Transport
- Hindustan Petroleum (~2 km)
- Malad (~2 km)
- Dahanukarwadi (~2 km)
- Goregaon Bus Station East (~4 km)
- Chhatrapati Shivaji Maharaj International Airport (~16 km)
- Navi Mumbai International Airport (~46 km)
-
Shopping & Dining
- 1441 Pizzeria (<1 km)
- Yash Mart (<1 km)
- Circle Cafe (<1 km)
- Infiniti Mall (<1 km)
- Borivali Municpal Market (~7 km)
- Shoppers Stop (~12 km)
-
Healthcare
- The Children's Hospital Mumbai - Best child specialist in Mumbai (<1 km)
- Navkar Skin Hair And Laser Clinic (<1 km)
- Care first pharmacy (<1 km)
- Apollo Pharmacy (<1 km)
- Dr. Akash Dhuru - Cancer Specialist Surgeon (<1 km)
- Dr. Amit Jain renowned Spine specialist in mumbai (~2 km)
-
Education
- Shri Balaji International School (<1 km)
- Our Lady of Lourdes Church & St.Annes School Compound (<1 km)
- KES College Ground (~2 km)
- Indira Gandhi Institute of Development Research (~7 km)
- Just Books (~8 km)
- Indian Institute of Technology Bombay (~14 km)
-
Leisure & Entertainment
- MovieTime Cinema (<1 km)
- aarogyam dhanasampada (<1 km)
- Goregaon Sport Complex (~1 km)
- Mumbai Football Arena (~10 km)
- Veermata Jijabai Bhosale Zoo & Botanical Garden (~33 km)
- Willingdon Sports Club (~34 km)
-
Services
- ICICI Bank (<1 km)
- Yes Bank ATM (<1 km)
- Malwani Fire Station (~2 km)
- Kharodi Post Office (India Post) (~2 km)
- Bangur Nagar Link Road Police Station (~2 km)
- Electoral Registration Officer (~3 km)
-
Religious Places
- Marimman Temple (<1 km)
- Gurudwara (<1 km)
- Our Lady of Lourdes Church, Orlem (<1 km)
- BAPS Shri Swaminarayan Mandir (~2 km)
- Mosque (~2 km)
- Saint Anthony's Church (~4 km)
-
Business & Hospitality
- Grand Hometel (~2 km)
- Industrial Estate (~3 km)
- Radisson Hotel Mumbai Goregaon (~3 km)
- All India Radio - AIR (~4 km)
- Nirlon Knowledge Park (~6 km)
- Nesco IT Park (~7 km)
- Project ID
- J657119255
- Updated
- Searches
- 526
- Views
- 523