DB Orchid Ozone - Dahisar East, Mumbai

Builder
DB Realty
Construction
Under Construction
Completion
Dec, 2024
Properties
Apartments
RERA
P51700003433

Description

Paradise abode

DB Orchid Ozone is a perfect residential project by DB Realty located at Dahisar (East), Mumbai. This project will let you experience the joys of living in a community, blessed with families from different walks of life which offers 2 & 3 Bhk apartments ranging between 585- 882 sq.ft. which is spread over the total area of 14 acre of land.
Amenities
  • Swimming Pool
  • Children's play area
  • Club House
  • Landscaped Gardens
  • Jogging Track
  • Power Backup
  • Lift Available
  • Rain Water Harvesting
  • 24*7 Security
  • Car Parking
  • Gymnasium
  • Vaastu Compliant
DB Realty, established in late seventies, real estate development company that has been built on a strong reputation of excellence through quality. Today, the Group is one of India's top Real Estate developers, with presence in Commercial, Residential, Hospitality, Retail, IT Parks and Gated communities. Its existing product portfolio ranges from upscale buildings, lavish villas and some of the most elite malls in the country, with new developments coming up at a fast pace.

Highlights

  • Security Guards
  • Fire Alarm
  • Electronic Security
  • Balcony
  • Reserved Parking
  • Marble Flooring
  • Visitor Parking
  • Maintenance Staff
  • Water Supply / Storage
  • Waste Disposal
  • Power Back-up
  • Club / Community Center
  • Lifts

Configurations

Type Area Possession Price *
1BHK Apartment585 SqFeetImmediate/Ready to move₹ 60 lakhs
2BHK Apartment882 SqFeetImmediate/Ready to move₹ 80 lakhs
* Data has been collected from publicly available sources and may not be up to date.

RERA

P51700003433 DB Ozone Lapsed 96% built

Confirmed with MahaRERA on 21 Sep 2026. Registered as "DB Ozone".

Promoter
NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED
Registered on
5 Aug 2017
Proposed completion
Dec 2024 (originally Dec 2019)
Project type
Residential / Group Housing
Planning authority
Others
Address as filed
General A K Vaidya Marg, Goregaon East, Mira-Bhayandar (M Corp.), Thane, Thane, 400063
Land area
38,401 sq m (413,354 sq ft)
Sanctioned built-up area
161,994 sq m (1,743,746 sq ft)
Buildings
Building No 28 (25 floors); Building No 1 (24 floors); Building No 2 (24 floors); Building No 3 (24 floors); Building No 4 (24 floors); Building No 7 (24 floors); Building No 8 (25 floors); Building No 6 (26 floors); Building No 9 (24 floors); Building No 10 (24 floors); Building No 11 (26 floors); Building No 12 (26 floors); Building No 14 (24 floors); Building No 15 (26 floors); Building No 16 (25 floors); Building No 17 (24 floors); Building No 18 (26 floors); Building No 20 (24 floors); Building No 21 (25 floors); Building No 22 (25 floors); Building No 23 (24 floors); Building No 24 (26 floors); Building No 27 (26 floors); Building No 29 (24 floors); Building No 30 (26 floors)
Parking
Open Space 0, Closed/Covered 1563
Complaints on the portal
71
BuildingUnit typeCarpet areaUnits
Building No 28B28 X03 EVEN 1BHK 33 sq m (360 sq ft) 16
Building No 28B28 X01 ODD 1.5BHK 45 sq m (479 sq ft) 10
Building No 28B28 X02 EVEN 2BHK 51 sq m (554 sq ft) 30
Building No 28B28 X01 EVEN 1.5BHK 45 sq m (487 sq ft) 10
Building No 28B28 X02 ODD 2BHK 51 sq m (552 sq ft) 30
Building No 28B28 X04 EVEN 2BHK 50 sq m (534 sq ft) 18
Building No 28B28 X04 ODD 2BHK 50 sq m (540 sq ft) 20
Building No 28B28 X03 ODD 1BHK 34 sq m (362 sq ft) 20
Building No 1B1 X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 1B1 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 1B1 X02 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 1B1 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 1B1 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 1B1 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 2B2 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 2B2 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 2B2 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 2B2 X02 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 2B X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 2B2 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 3B3 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 3B3 X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 3B3 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 3B3 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 3B3 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 3B3 X02 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 4B4 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 4B4 X02 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 4B4 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 4B4 X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 4B4 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 4B4 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 7B7 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 7B7 XO2 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 7B7 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 7B7 X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 7B7 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 7B7 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 8B8 X01 ODD 1.5BHK 45 sq m (489 sq ft) 10
Building No 8B8 X02 ODD 2BHK 52 sq m (558 sq ft) 10
Building No 8B8 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 8B8 X01 EVEN 1.5BHK 45 sq m (489 sq ft) 10
Building No 8B8 X02 EVEN 2BHK 52 sq m (558 sq ft) 10
Building No 8B8 X03 EVEN 1BHK 34 sq m (363 sq ft) 36
Building No 6B6 X03 ODD 2BHK 49 sq m (531 sq ft) 22
Building No 6B6 X04 ODD 2BHK 46 sq m (499 sq ft) 11
Building No 6B6 X03 EVEN 2BHK 49 sq m (526 sq ft) 20
Building No 6B6 X04 EVEN 2BHK 46 sq m (495 sq ft) 8
Building No 6B6 X01 ODD 2BHK 52 sq m (556 sq ft) 33
Building No 6B6 X02 ODD 1.5BHK 45 sq m (480 sq ft) 11
Building No 6B6 X02 EVEN 1.5BHK 45 sq m (486 sq ft) 10
Building No 6B6 X01 EVEN 2BHK 52 sq m (554 sq ft) 30
Building No 9B9 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 9B9 X02 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 9B9 XO3 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 9B9 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 9B9 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 9B9 X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 10B10 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 10B10 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 10B10 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 10B10 X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 10B10 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 10B10 X02 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 11B11 X02 EVEN 1BHK 34 sq m (362 sq ft) 16
Building No 11B11 X01 ODD 2BHK 51 sq m (553 sq ft) 44
Building No 11B11 X02 ODD 1BHK 33 sq m (358 sq ft) 22
Building No 11B11 X01 EVEN 2BHK 51 sq m (547 sq ft) 40
Building No 12B12 X02 EVEN 1BHK 33 sq m (360 sq ft) 16
Building No 12B12 X03 EVEN 2BHK 52 sq m (558 sq ft) 20
Building No 12B12 X01 EVEN 1BHK 34 sq m (369 sq ft) 20
Building No 12B12 X03 ODD 2BHK 52 sq m (561 sq ft) 22
Building No 12B12 X02 ODD 1BHK 33 sq m (360 sq ft) 22
Building No 12B12 X01 ODD 1BHK 34 sq m (367 sq ft) 22
Building No 14B14 X02 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 14B14 X03 ODD 2BHK 52 sq m (560 sq ft) 20
Building No 14B14 X01 EVEN 1BHK 34 sq m (362 sq ft) 48
Building No 14B14 X01 ODD 1BHK 34 sq m (365 sq ft) 20
Building No 14B14 X02 EVEN 2BHK 51 sq m (554 sq ft) 18
Building No 15B15 X01 ODD 1BHK 33 sq m (356 sq ft) 22
Building No 15B15 X02 ODD 1BHK 33 sq m (360 sq ft) 44
Building No 15B15 X01 EVEN 1BHK 33 sq m (358 sq ft) 20
Building No 15B15 X02 EVEN 1BHK 34 sq m (364 sq ft) 36
Building No 16B16 X02 EVEN 2BHK 52 sq m (559 sq ft) 20
Building No 16B16 X02 ODD 2BHK 52 sq m (557 sq ft) 20
Building No 16B16 X01 EVEN 1BHK 33 sq m (360 sq ft) 36
Building No 16B16 X01 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 17B17 X01 ODD 1BHK 34 sq m (365 sq ft) 20
Building No 17B17 X02 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 17B17 X01 EVEN 1BHK 34 sq m (362 sq ft) 48
Building No 17B17 X02 EVEN 2BHK 51 sq m (554 sq ft) 18
Building No 17B17 X03 ODD 2BHK 52 sq m (560 sq ft) 20
Building No 18B18 X03 EVEN 2BHK 51 sq m (552 sq ft) 20
Building No 18B18 X02 EVEN 2BHK 49 sq m (527 sq ft) 20
Building No 18B18 X01 ODD 1BHK 33 sq m (355 sq ft) 22
Building No 18B18 X04 ODD 2BHK 48 sq m (522 sq ft) 11
Building No 18B18 X01 EVEN 1BHK 33 sq m (353 sq ft) 20
Building No 18B18 X04 EVEN 2BHK 49 sq m (526 sq ft) 8
Building No 18B18 X03 ODD 2BHK 51 sq m (554 sq ft) 22
Building No 18B18 X02 ODD 2BHK 50 sq m (534 sq ft) 22
Building No 20B20 X02 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 20B20 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 20B20 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 20B20 X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 20B20 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 20B20 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 21B21 X01 ODD 1.5BHK 45 sq m (489 sq ft) 10
Building No 21B21 X02 ODD 2BHK 52 sq m (558 sq ft) 10
Building No 21B21 X01 EVEN 1.5BHK 45 sq m (489 sq ft) 10
Building No 21B21 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 21B21 X03 EVEN 1BHK 34 sq m (363 sq ft) 36
Building No 21B21 X02 EVEN 2BHK 52 sq m (558 sq ft) 10
Building No 22B 22 X01 ODD 1 BHK 33 sq m (360 sq ft) 40
Building No 22B 22 X02 ODD 2 BHK 52 sq m (557 sq ft) 20
Building No 22B 22 X01 EVEN 1 BHK 33 sq m (360 sq ft) 36
Building No 22B 22 X02 EVEN 2 BHK 52 sq m (559 sq ft) 20
Building No 2323 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 2323 X02 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 2323 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 2323 X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 2323 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 2323 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 2424 X02 ODD 1BHK 33 sq m (358 sq ft) 22
Building No 2424 X01 EVEN 2BHK 51 sq m (547 sq ft) 40
Building No 2424 X02 EVEN 1BHK 34 sq m (362 sq ft) 16
Building No 2424 X01 ODD 2BHK 51 sq m (553 sq ft) 44
Building No 2727 X03 EVEN 2BHK 50 sq m (533 sq ft) 20
Building No 2727 X02 EVEN 2BHK 52 sq m (556 sq ft) 20
Building No 2727 X01 ODD 2BHK 52 sq m (556 sq ft) 11
Building No 2727 X02 ODD 2BHK 51 sq m (549 sq ft) 22
Building No 2727 X03 ODD 2BHK 49 sq m (532 sq ft) 22
Building No 2727 X01 EVEN 2BHK 48 sq m (517 sq ft) 8
Building No 2929 X03 EVEN 1BHK 34 sq m (362 sq ft) 30
Building No 2929 X02 EVEN 2BHK 52 sq m (557 sq ft) 27
Building No 2929 X01 EVEN 1.5BHK 45 sq m (488 sq ft) 9
Building No 2929 X03 ODD 1BHK 33 sq m (360 sq ft) 40
Building No 2929 X01 ODD 1.5BHK 45 sq m (487 sq ft) 10
Building No 2929 X02 ODD 2BHK 52 sq m (560 sq ft) 30
Building No 3030 X02 EVEN 1.5BHK 45 sq m (486 sq ft) 10
Building No 3030 X01 ODD 2BHK 52 sq m (556 sq ft) 33
Building No 3030 X01 EVEN 2BHK 52 sq m (554 sq ft) 30
Building No 3030 X04 EVEN 2BHK 46 sq m (495 sq ft) 8
Building No 3030 X03 EVEN 2BHK 49 sq m (526 sq ft) 20
Building No 3030 X03 ODD 2BHK 49 sq m (531 sq ft) 22
Building No 3030 X02 ODD 1.5BHK 45 sq m (480 sq ft) 11
Building No 3030 X04 ODD 2BHK 46 sq m (499 sq ft) 11
Quarterly returnFiledBuiltUnits booked
Q2 FY 2024-2025 not filed - in default - -
Q3 FY 2024-2025 not filed - in default - -
Construction progress as reported to the portal

Building No 28

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 98%
  • Sanitary Fittings within the flats / premises: 78%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 98%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 82%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 76%

Building No 1

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Building No 2

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Building No 3

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Building No 4

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Building No 7

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 89%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 98%

Building No 8

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 93%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 98%

Building No 6

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 79%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 98%

Building No 9

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 87%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 98%

Building No 10

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 88%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 98%

Building No 11

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 72%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 99%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 99%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

Building No 12

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 98%
  • Sanitary Fittings within the flats / premises: 70%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 98%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 98%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

Building No 14

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 98%
  • Sanitary Fittings within the flats / premises: 81%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 98%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 98%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

Building No 15

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 97%
  • Sanitary Fittings within the flats / premises: 73%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 97%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 98%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

Building No 16

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 98%
  • Sanitary Fittings within the flats / premises: 81%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 98%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 98%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

Building No 17

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 98%
  • Sanitary Fittings within the flats / premises: 81%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 98%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 98%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

Building No 18

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 98%
  • Sanitary Fittings within the flats / premises: 78%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 98%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 98%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 78%

Building No 20

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 96%
  • Sanitary Fittings within the flats / premises: 77%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 96%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 91%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 77%

Building No 21

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 96%
  • Sanitary Fittings within the flats / premises: 75%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 96%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 91%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 77%

Building No 22

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 96%
  • Sanitary Fittings within the flats / premises: 77%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 96%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 91%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 77%

Building No 23

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 96%
  • Sanitary Fittings within the flats / premises: 72%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 96%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 91%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 74%

Building No 24

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 96%
  • Sanitary Fittings within the flats / premises: 70%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 96%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 94%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 80%

Building No 27

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 90%
  • Sanitary Fittings within the flats / premises: 78%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 96%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 82%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 76%

Building No 29

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 97%
  • Sanitary Fittings within the flats / premises: 82%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 82%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 76%

Building No 30

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 90%
  • Sanitary Fittings within the flats / premises: 66%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 82%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 76%

Common areas and facilities

  • Internal Roads & Footpaths: 80% - Minimum 6m road width
  • Water Supply: 55% - Fresh water supply from MCGM
  • Sewerage (Chamber, Lines, Septic Tank , STP): 75% - Dispose thru STP & bal treated water thru drains
  • Storm Water Drains: 100% - Rain water downtake to rainwater harvesting tank
  • Landscaping & Tree Planting: 0% - Proposed ground floor and podium top
  • Street Lighting: 70% - lighting designed as per Authority regulation
  • Treatment And Disposal Of Sewage And Sullage Water: 75% - Into STP & reused treated water disposed to drains
  • Solid Waste Management And Disposal: 30% - As per waste management rules of MBMC
  • Water conservation /Rain water harvesting: 0% - Rainwater harvesting tanks
  • Energy managemcnt: 40% - Power supply through utility provider
  • Fire protection and fire safety requirements: 60% - As per CFO
  • Electrical meter room, sub-station, receiving station: 60% - MBMC and NBC Norms
  • Aggregate area of recreational Open Space: 0% - Meter Room and sub-station & Receiving stations
  • Other facilities: 0% - Clubhouse & swimming pool
RERA details are as filed by the promoter with the state authority and as read from its portal on the date shown; PropertyWala.com has not verified them independently.

Reviews

Be the first to write a review of DB Orchid Ozone and become a Project expert!
  • Post an informative review and get 1 additional basic property listing FREE of cost*.
  • Your review will be displayed prominently on your property listing page and other pages on the website.
  • For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
* The review must be factual, informative and unique.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of DB Orchid Ozone
Cons:
Enter some negative aspects of DB Orchid Ozone

Location

DB Orchid Ozone, Dahisar East, Mumbai - 400068 (Maharashtra)

* Location may be approximate

Landmarks

  • Offices

    • SAMAJ KALYAN KENDRA HALL (<2km)
    • Anant Royal Banquet (<10km)
    • sanskruti Hall (<10km)
  • Shopping

    • Top Line (<6km)
    • Tsangpo
    • Soul Foods (<11km)
    • Coffee & Tea Instant Premix (<11km)
    • Maa Mamta Collection (<3km)
    • Neelkamal Medical & General Stores (<3km)
    • Kala Medical And General Stores (<3km)
    • Emeis (<4km)
    • Ganga Jamuna Saraswati Chana Shop (<6km)
    • Jay Bhavani Kirana And General Store (<7km)
    • Kakade Discount Store (<7km)
    • Dinoo
    • The Hungry Birds (<10km)
    • A1 Coffee & Tea Instant Premix Powder (<11km)
    • Shubh Laxmi General Store (<12km)
    • Kb
    • Bhawani Provision Store (<13km)
    • The Main Street (<13km)
    • Aashapura Convenience Stores (<13km)
    • Navina General Store (<14km)
  • Education

    • ETENCA (<6km)
    • V.K. Krishna Menon Academy (<8km)
    • Uttkarsh Vidya Mandir (<12km)
    • St Paul
    • Maharani Saibai Vidya Mandir (<11km)
    • Lets Talk (<5km)
    • Dr. S.Radhakrishnan International School (<8km)
    • Podar Jumbo Kids (<3km)
    • Inner Space Counseling Center (<13km)
    • St. Xavier
    • Blue Heaven Nursery (<5km)
    • English Speaking Institute in Mumbai (<5km)
    • Prerna Academy (<4km)
    • The Don Bosco High School (<6km)
    • St. Louis’ High School Dahisar (<3km)
    • Himalaya High School (<8km)
    • S M Public High School (<8km)
    • Nursery Borivali Chikowadi (<8km)
    • Mother
  • Transportation

    • Jobs In Airline (<7km)
    • Helper (<11km)
    • RMP Helipad (<11km)
    • international courier service (<12km)
    • Hawre Helipad (<13km)
  • Hotels & Guest Houses

    • Eskay Resort (<6km)
    • GCC Hotel and Club (<3km)
    • OYO Apartments Malad Raheja Complex Road (<11km)
    • OYO 618 Maharaja Hotel (<2km)
    • D69 residency (<0.5km)
    • Monalisa Spacious Room (<7km)
    • Shantidhoot Society (<11km)
    • OYO 28681 Tuliip - Kanjurmarg (<10km)
    • Suvi Palace (<10km)
    • Hexa A1 Stay (<12km)
    • Hotel Sea N Rock (<5km)
    • Room Maangta 112 @ Andheri (<13km)
    • OYO 35522 Global Marketing Service Apartment (<13km)
    • OYO 10166 Hotel D69 Residency (<0.5km)
    • Executive Orchid Apt (<14km)
    • Tripvillas @ Dream Home (<14km)
    • Surya Prakash Lodging (<1km)
    • Room Maangta 218 @ Thane East (<1km)
    • Shreya Lodgiing (<6km)
  • Recreation

    • INOX Raguleela (<8km)
    • Movie time cinema (<13km)
    • INOX (<0.5km)
    • Movie Time (<2km)
    • Phoenix Films (<4km)
    • PVR Cinemas - Mira Road (<5km)
    • Maxus Cinemas (<7km)
    • Carnival Cinemas Annex Mall Borivali (<7km)
    • INOX (<8km)
    • PVR Milap Kandivali (<11km)
    • City Studio (<11km)
    • Ramdev Studio (<11km)
    • PVR Growel / Kandivali East (<9km)
    • PVR Cinemas (<13km)
    • Sona Gold Digital Cinema (<4km)
    • PVR ICON - Oberoi (<14km)
    • Thakur Miraj Cinemas (<8km)
    • Inox Movie Vishnu Shivam Mall (<8km)
    • Rassaz Multiplex (<4km)
    • Bharti Art Studio (<1km)
  • Banks & ATMs

    • Corporation Bank ATM (<3km)
    • IDBI Bank (<8km)
    • Federal Bank (<7km)
    • IDBI Bank ATM (<10km)
    • IDBI Bank (<12km)
    • Syndicate Bank ATM (<3km)
    • ICICI Bank ATM (<6km)
    • Abhyudya Co - Op Bank & Atm (<10km)
    • Axis Bank ATM (<5km)
    • Oriental Bank Of Commerce bhayandar west branch (<8km)
    • Union Bank of India (<5km)
    • IndusInd Bank (<7km)
    • IndusInd Bank ATM (<8km)
    • Cosmos Bank ATM (<8km)
    • Union Bank Of India ATM (<5km)
    • Axis Bank ATM (<6km)
    • Dena Bank ATM (<2km)
    • HDFC Bank ATM (<8km)
    • Bank of Baroda ATM (<9km)
  • Hospitals & Healthcare

    • Shivam Dental Clinic (<3km)
    • Synergy Dental Clinic (<5km)
    • Lifetime Smiles Dental Clinic (<4km)
    • FabSmyle Dental clinic (<8km)
    • Dr Mrugank - Lifetime Smiles Dental Clinic (<4km)
    • Smile Zone Dental Care Centre (<3km)
    • Dr Pritam Assrani - Akshar Dental Solutions (<8km)
    • Sharda Dental Clinic (<4km)
    • Smile Designers Dental Clinic (<8km)
    • Swasth Dental Clinic (<2km)
    • Dr. Shah
    • Dentist In Mira Road Smiling Teeth (<3km)
    • The smile zone (<2km)
    • Smiles Ahead Clinic (<5km)
    • Dr. Khot
    • Dr Shalini Agarwal (<8km)
    • Easel Dental Laboratory (<8km)
    • Central Dental Clinic (<3km)
    • Dr. Gauri P. Maligi (<5km)
    • SMILE CREATIONS DENTAL CLINIC (<2km)
  • Religious Places

    • Immanuel Mar Thoma Church (<3km)
    • St. Louis Church (<3km)
    • New Life Fellowship (<6km)
    • Sacred Heart Catholic Church (<7km)
    • St. Gregorios Orthodox Church (<5km)
    • St. Thomas Church (<3km)
    • Mira Road Assembly Of God Church (<5km)
    • Our Lady of Remedy Church (<8km)
    • The Crown Of Life Ministries Mira Road (<3km)
    • Holy Cross Church (<4km)
    • Our Lady of the Immaculate Conception Church (<4km)
    • Methodist Gujarati & Marathi Borivali Church (<4km)
    • New Testament Church (<9km)
    • Kingdom Hall of Jehovah
    • Our Lady Of Nazareth Church (<7km)
    • Elim Church Poisar (<9km)
    • St. Kuriakose Elias Chavara Church (<9km)
    • Nativity of Our Lord Church (<10km)
    • Holy Cross Chapel (<10km)
    • Aurlience Solutions (<11km)
  • Restaurants & Clubs

    • Baskin Robbins (<8km)
    • The French Connection (<8km)
    • Monginis Cake Shop (<3km)
    • Monginis (<8km)
    • Birdy
    • Monginis Cake Shop (<8km)
    • Savita Enterprises (<2km)
    • Ribbons & Balloons (<9km)
    • Sweet Treats (<10km)
    • Happiness Deli (<8km)
    • Janta Bakery (<2km)
    • Caek Cafe (<2km)
    • Denish - Bhagwati food (<2km)
    • International Baking Company (<2km)
    • Nice & Yummy (<2km)
    • Melting Moments Cake Shop (<2km)
    • Monginis Cake Shop (<2km)
    • Melting Moment Cake shop (<3km)
Project ID
J301200119
Updated
Searches
6403
Views
1834