20+ podium level lifestyle amenities
Neelkanth Palm Avenue is an elegant high-rise residential development project located in Sector 9, Ghansoli, Navi Mumbai. The project development offers spacious 2 BHK and 3 BHK residential apartments ranging from 780 to 1125 sq.ft.The project spans approximately 1.24 acres of land. The project features two wings of G+38 storeys, natural light, ventilation, open views and 231 units.
Amenities:
- Grand Clubhouse
- Landscaped Gardens
- Outdoor Seating
- Swimming Pool
- Gymnasium
- Jogging Track
- Sports Courts
- Indoor Games
- Kids Play Zone
- Covered Parking
- Power Backup
- High-Speed Elevators
Neelkanth Infratech Builders is a Navi Mumbai–based real estate developer known for delivering quality residential and commercial projects with a focus on modern design, solid construction, and customer-centric planning. Established in 2012 , the company has steadily built a reputation for reliability, transparent dealings, and timely project execution.
Highlights
- Grand Clubhouse
- Landscaped Gardens
- Outdoor Seating
- Swimming Pool
- Gymnasium
- Jogging Track
- Sports Courts
- Indoor Games
- Kids Play Zone
- Covered Parking
- Power Backup
- High-Speed Elevators
Configurations
| Type | Area | Possession | Price * |
|---|---|---|---|
| 2BHK Apartment | 780 SqFeet | Within 4 Years | ₹ 1.7 crore |
| 3BHK Apartment | 1,125 SqFeet | Within 4 Years | ₹ 2.45 crores |
RERA
P51700052959 NEELKANTH PALM AVENUE Active 65% built
Confirmed with MahaRERA on 21 Sep 2026. Registered as "NEELKANTH PALM AVENUE".
- Promoter
- NEELKANTH INFRATECH
- Registered on
- 6 Oct 2023
- Proposed completion
- Apr 2030 (originally Dec 2029)
- Project type
- Others
- Planning authority
- Others
- Address as filed
- PLOT NO-23&24,SECTOR 09, GHANSOLI,NAVI MUMBAI, Navi Mumbai (M Corp.), Thane, Thane, 400701
- Land area
- 5,027 sq m (54,114 sq ft)
- Sanctioned built-up area
- 26,215 sq m (282,185 sq ft)
- Buildings
- A-wing (45 floors) - 77 of 137 available; B-wing (45 floors) - 69 of 164 available
- Parking
- Open Space 0, Closed/Covered 454
| Building | Unit type | Carpet area | Units |
|---|---|---|---|
| A-wing | Shop | 58 sq m (629 sq ft) | 1 |
| A-wing | Shop | 72 sq m (775 sq ft) | 1 |
| A-wing | Shop | 70 sq m (755 sq ft) | 1 |
| A-wing | Shop | 70 sq m (750 sq ft) | 1 |
| A-wing | Shop | 69 sq m (745 sq ft) | 1 |
| A-wing | Shop | 71 sq m (768 sq ft) | 1 |
| A-wing | Shop | 69 sq m (744 sq ft) | 1 |
| A-wing | Shop | 68 sq m (732 sq ft) | 1 |
| A-wing | Shop | 56 sq m (604 sq ft) | 1 |
| A-wing | Shop | 71 sq m (763 sq ft) | 1 |
| A-wing | 2BHK | 59 sq m (633 sq ft) | 32 |
| A-wing | 2BHK | 59 sq m (640 sq ft) | 31 |
| A-wing | 2BHK | 63 sq m (679 sq ft) | 32 |
| A-wing | Shop | 72 sq m (772 sq ft) | 1 |
| A-wing | Shop | 70 sq m (755 sq ft) | 1 |
| A-wing | Shop | 70 sq m (750 sq ft) | 1 |
| A-wing | Shop | 69 sq m (738 sq ft) | 1 |
| A-wing | Shop | 71 sq m (767 sq ft) | 1 |
| A-wing | Shop | 66 sq m (712 sq ft) | 1 |
| A-wing | Shop | 57 sq m (616 sq ft) | 1 |
| A-wing | Shop | 56 sq m (599 sq ft) | 1 |
| A-wing | Shop | 55 sq m (590 sq ft) | 1 |
| A-wing | 2BHK | 63 sq m (675 sq ft) | 32 |
| B-wing | 3BHK | 89 sq m (959 sq ft) | 32 |
| B-wing | SERVICE QUARTERS | 30 sq m (318 sq ft) | 5 |
| B-wing | 2 BHK EWS | 48 sq m (519 sq ft) | 5 |
| B-wing | 2 BHK EWS | 47 sq m (507 sq ft) | 8 |
| B-wing | 1 BHK EWS | 33 sq m (350 sq ft) | 5 |
| B-wing | 2BHK | 60 sq m (643 sq ft) | 31 |
| B-wing | SERVICE QUARTERS | 39 sq m (425 sq ft) | 5 |
| B-wing | 2BHK | 59 sq m (635 sq ft) | 32 |
| B-wing | 2BHK | 64 sq m (686 sq ft) | 32 |
| Quarterly return | Filed | Built | Units booked |
|---|---|---|---|
| Q3 FY 2023-2024 | 29 May 2025 | - | - |
| Q4 FY 2023-2024 | 29 May 2025 | - | - |
| Q1 FY 2024-2025 | 29 May 2025 | - | - |
| Q2 FY 2024-2025 | 29 May 2025 | - | - |
| Q3 FY 2024-2025 | 29 May 2025 | - | - |
| Q4 FY 2024-2025 | not filed - in default | - | - |
| Q1 FY 2025-2026 | 13 Oct 2025 | - | - |
| Q2 FY 2025-2026 | 13 Nov 2025 | - | - |
| Q3 FY 2025-2026 | 31 Jan 2026 | - | - |
| Q4 FY 2025-2026 | 9 May 2026 | - | - |
| Q1 FY 2026-2027 | 20 Jul 2026 | - | - |
Construction progress as reported to the portal
A-wing
- Excavation: 100%
- Basement (if any): 0%
- Podiums (if any): 100%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 85%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 60%
- Sanitary Fittings within the flats / premises: 20%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 65%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
B-wing
- Excavation: 100%
- Basement (if any): 0%
- Podiums (if any): 85%
- Plinth: 100%
- Stilt Floor: 85%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 62%
- Sanitary Fittings within the flats / premises: 20%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 40%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
Common areas and facilities
- Water Supply: 0% - NA
- Sewerage (Chamber, Lines, Septic Tank , STP): 75% - NA
- Landscaping & Tree Planting: 20% - NA
- Water conservation /Rain water harvesting: 35% - NA
- Fire protection and fire safety requirements: 10% - NA
- Electrical meter room, sub-station, receiving station: 0% - NA
Reviews
Write a review
Be the first to write a review of Neelkanth Palm Avenue and become a Project expert!
- Post an informative review and get 1 additional basic property listing FREE of cost*.
- Your review will be displayed prominently on your property listing page and other pages on the website.
- For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of Neelkanth Palm Avenue
Enter some positive aspects of Neelkanth Palm Avenue
Cons:
Enter some negative aspects of Neelkanth Palm Avenue
Enter some negative aspects of Neelkanth Palm Avenue
Location
Neelkanth Palm Avenue, Ghansoli, Navi Mumbai - 400701 (Maharashtra)
Nearby
-
Transport
- Ghansoli (~2 km)
- Koparkhairane NMMT Bus Station (~3 km)
- Hindustan Petroleum (~3 km)
- Jagruti Nagar (~14 km)
- Chhatrapati Shivaji Maharaj International Airport (~19 km)
- Navi Mumbai International Airport (~23 km)
-
Shopping & Dining
- Casino Cafe | Cafe in Ghansoli Navi Mumbai (<1 km)
- Pizza Hut (<1 km)
- DMart (~1 km)
- Satra Plaza (~6 km)
- APMC Grain Market (~6 km)
- bhakti (~12 km)
-
Healthcare
- Majisa Medico (<1 km)
- New Life Medical (~2 km)
- Dr. Dive S Eye Clinic (~3 km)
- Reliance Hospital (~4 km)
- apple hospital (~4 km)
- Spandan Healthcare center (~4 km)
-
Education
- Shrimati Indira Gandhi College of Engineering (<1 km)
- Terna Orchids International Schoool (~2 km)
- North Point School (~3 km)
- Dhirubhai Ambani Knowledge City (~3 km)
- Cht.Sahu Maharaj Vachnalaya (~7 km)
- Indian Institute of Technology Bombay (~12 km)
-
Leisure & Entertainment
- Central Park (~2 km)
- Navi Mumbai Sports Association (~7 km)
- Dadoji Konddev Stadium (~12 km)
- Inox (~14 km)
- Kharghar Valley Golf Course (~14 km)
- Butterfly Park (~15 km)
-
Services
- Axis Bank (<1 km)
- HDFC Bank ATM (~1 km)
- Koparkhairne Fire Station (~2 km)
- MIDC Mahape (~3 km)
- KK POLICE STATION (~4 km)
- India Post (~6 km)
-
Religious Places
- Gurudwara Guru Singh Sabha, koperKhairane (~3 km)
- Jai Hanuman Mandir (~3 km)
- Koparkhairane Jama Masjid (~3 km)
- Mahalaxmi Mandir KK (~4 km)
- ganesh mandir (~4 km)
- SHRI DATTA GURU MANDIR (~4 km)
-
Business & Hospitality
- Country Inn Hotel & Suites (~3 km)
- Reliance Corporate Park (~3 km)
- Millennium Business Park, Mahape Village (~4 km)
- SIEMENS (~5 km)
- Navi Mumbai Marriott Hotel (~9 km)
- CEAT Tyre (~9 km)
- Project ID
- J811925919
- Updated
- Searches
- 440
- Views
- 440