Elevation
Side View
Location Map
 6

Kohinoor Sapphire 2 - Tathawade, Pune

Builder
Kohinoor Group
Construction
Completed
Completion
Sep, 2024
Properties
Apartments
RERA
P52100026685

Description

best of joys and conveniences

Kohinoor Sapphire 2 by Kohinoor Group is offering spacious 2 bhk apartments in the size ranges in between 659 to 669 sqft.The project has 2 Location has excellent connectivity & it is located in Tathawade at the crux of Pimpri-Chinchwad right off the Mumbai Highway national expressway close to Hinjawadi, Mahalunge, Baner near existing and upcoming communities & facilities.

Amenities :
  • Gymnasium
  • Clubhouse
  • Swimming Pool
  • Indoor Games
  • Amphitheatre
  • Kids Play area
  • Lift
  • Car Parking
  • Power Backup
Established by Mr. Krishnakumar Goyal, Kohinoor Group has created a significant wave in the real estate sector with its landmark projects. Although the group commenced its operations in 1983, it began construction and development under the name of Kohinoor Constructions in 1989. The company has built a thriving relationship with its customers based on the solid foundation of trust, integrity, and transparency.

Highlights

  • Power Back-up
  • Maintenance Staff
  • Water Supply / Storage
  • Rain Water Harvesting
  • Lifts
  • High Speed Internet
  • Security Guards
  • Electronic Security
  • Intercom Facility
  • Balcony
  • Reserved Parking
  • Swimming Pool
  • Park
  • Fitness Centre / GYM
  • Club / Community Center

Configurations

Type Area Possession Price *
2BHK Apartment659 SqFeetImmediate/Ready to move₹ 59.1 lakhs
* Data has been collected from publicly available sources and may not be up to date.

RERA

P52100026685 KOHINOOR SAPPHIRE II Completed

Confirmed with MahaRERA on 24 Sep 2026. Registered as "KOHINOOR SAPPHIRE II".

Promoter
RISING ASSOCIATES
Registered on
21 Oct 2020
Proposed completion
Sep 2024
Project type
Residential / Group Housing
Planning authority
Others
Address as filed
S NO 9 2B AND S NO 10 1 VILLAGE TATHAWADE TAL MULSHI DIST PUNE, Tathwade, Mulshi, Pune, 411033
Land area
11,272 sq m (121,335 sq ft)
Sanctioned built-up area
7,910 sq m (85,145 sq ft)
Buildings
A (12 floors); B (12 floors); C (14 floors); D (14 floors); E (14 floors); F (14 floors); G (14 floors); H (14 floors); I (14 floors); MAHDA (12 floors)
Parking
Open Space 0, Closed/Covered 0
BuildingUnit typeCarpet areaUnits
A2BHK 48 sq m (521 sq ft) 37
A1BHK 36 sq m (382 sq ft) 2
B2BHK 48 sq m (521 sq ft) 37
B1BHK 36 sq m (382 sq ft) 2
C2BHK 48 sq m (521 sq ft) 43
C1BHK 36 sq m (382 sq ft) 1
D2BHK 48 sq m (521 sq ft) 44
D1BHK 36 sq m (382 sq ft) 1
E1BHK 36 sq m (382 sq ft) 2
E2BHK 48 sq m (521 sq ft) 44
F1BHK 36 sq m (382 sq ft) 2
F2BHK 47 sq m (504 sq ft) 44
G2BHK 47 sq m (504 sq ft) 44
G1BHK 36 sq m (382 sq ft) 2
H1BHK 36 sq m (382 sq ft) 2
H2BHK 47 sq m (504 sq ft) 44
I1BHK 36 sq m (382 sq ft) 1
I2BHK 47 sq m (504 sq ft) 43
MAHDA1BHK 40 sq m (434 sq ft) 8
MAHDA1BHK 42 sq m (455 sq ft) 20
Quarterly returnFiledBuiltUnits booked
Q2 FY 2024-2025 not filed - in default - -
Construction progress as reported to the portal

A

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

B

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

C

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 55%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 95%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 80%

D

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 93%

E

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

F

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

G

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

H

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

I

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%

MAHDA

  • Excavation: 100%
  • Basement (if any): 80%
  • Podiums (if any): 90%
  • Plinth: 80%
  • Stilt Floor: 85%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 80%
  • Sanitary Fittings within the flats / premises: 0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 80%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 85%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 70%

Common areas and facilities

  • Internal Roads & Footpaths: 80% - WORK IN PROGRESS
  • Water Supply: 50% - WORK IN PROGRESS
  • Sewerage (Chamber, Lines, Septic Tank , STP): 85% - WORK IN PROGRESS
  • Storm Water Drains: 95% - WORK IN PROGRESS
  • Landscaping & Tree Planting: 50% - WORK IN PROGRESS
  • Street Lighting: 0% - Work Not started
  • Community Buildings: 80% - WORK IN PROGRESS
  • Treatment And Disposal Of Sewage And Sullage Water: 90% - WORK IN PROGRESS
  • Solid Waste Management And Disposal: 85% - WORK IN PROGRESS
  • Water conservation /Rain water harvesting: 5% - WORK IN PROGRESS
  • Energy managemcnt: 0% - WORK YET TO START
  • Fire protection and fire safety requirements: 95% - WORK YET TO START
  • Electrical meter room, sub-station, receiving station: 85% - WORK IN PROGRESS
RERA details are as filed by the promoter with the state authority and as read from its portal on the date shown; PropertyWala.com has not verified them independently.

Reviews

Be the first to write a review of Kohinoor Sapphire 2 and become a Project expert!
  • Post an informative review and get 1 additional basic property listing FREE of cost*.
  • Your review will be displayed prominently on your property listing page and other pages on the website.
  • For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
* The review must be factual, informative and unique.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of Kohinoor Sapphire 2
Cons:
Enter some negative aspects of Kohinoor Sapphire 2

Location

Kohinoor Sapphire 2, Tathawade, Pune - 411033 (Maharashtra)

* Location may be approximate

Landmarks

  • ATM/Bank/Exchange

    • State Bank of India (<0.5km)
    • State Bank of India Atm (<1km)
    • Bank of Maharashtra (<1km)
    • Idbi Bank (<1km)
    • Bank of India (<1km)
    • Lokmangal Multistate Co Operative Society-Dange Chowk (<1km)
    • Union Bank of India (<1km)
    • HDFC Bank (<1km)
    • Pune Jilla Madhyavarti Sahakari Bank (<1km)
    • Pune District Central Co-Operative Bank-Thergaon (<1km)
    • Axis Bank (<2km)
    • Axis Bank Atm (<2km)
    • Lokmangal Multistate Cooperative Society-Dange Chowk (<2km)
  • Petrol Station

    • Hindustan Petroleum (<0.5km)
    • Bharat Petroleum Corporation (<0.5km)
  • Public Transport

    • Dairy Farm (<0.5km)
    • Tathwade (<1km)
    • Kudale Farm (<2km)
    • Thergaon Phata (<2km)
    • Dange Chowk (<2km)
  • Restaurant & Shops

    • Creations Arts (<0.5km)
    • Mahalaxmi Super Market (<1km)
    • Om Super Shoppee (<1km)
    • Chamunda Super Market (<1km)
    • Gurukrupa Gift House & Novelties (<1km)
    • Maharashtra Super Shoppee (<1km)
    • New Choice Tailors (<1km)
    • Shivshakti Super Market (<1km)
    • Ramdev Traders (<1km)
    • Laxmi Narayan General Store (<1km)
    • Trimurti Textiles (<1km)
    • Paramar Super Market (<1km)
    • Mathaji Super Market (<1km)
    • Bhagyasri Collection (<1km)
    • Shri Samartha Tailors (<1km)
    • Arihant Collections (<1km)
    • Shri Purbaji Super Market (<1km)
    • Hanuman Trading (<1km)
    • Ramesh Mini Market (<2km)
    • Sanjay Super Market (<2km)
    • Padmawati Jewellers (<2km)
    • Radha Krushn Super Market (<2km)
    • Vijaysuper Market (<2km)
    • Bhagyalaxmi Sarees (<2km)
    • Bhagya Laxmi Sarees (<2km)
    • Shri Ganesh Jewelers (<2km)
    • Lady Fashion (<2km)
    • Fashion. Com (<2km)
    • Sadguru Footwear (<2km)
    • Raj Mens Wear & Collection (<2km)
    • Shiv Collection (<2km)
  • Hostel

    • Raviraj Heights (<1km)
    • Eon the Ecotel Hostel (<1km)
    • Oxford Boys Hostel (<1km)
    • Sayadri Boys Hostel (<1km)
  • Hospitals & Clinics

    • Sanjeevani Clinic (<1km)
    • Dawakhana (<1km)
    • Shivshree Clinic (<1km)
    • Pargaonkar Clinic (<1km)
    • Pulse Hospital (<1km)
    • Pulse Hospital-ER (<1km)
    • Peals Multispecialty Hospital-ER (<1km)
    • Peals Multispecialty Hospital (<1km)
    • Yashodeep Clinic (<1km)
    • Pet Magic (<1km)
    • Dr Jon Laboratory (<1km)
    • Ashwini Nursing Home & Laparoscopy Center-ER (<1km)
    • Ashwini Nursing Home & Laparoscopy Center (<1km)
    • Aarohi Clinic (<2km)
    • Rigved Clinic (<2km)
    • Unique Vision Optician (<2km)
    • Pimpari Hospital-ER (<2km)
    • Pimpari Hospital (<2km)
    • Apex Sonography Clinic (<2km)
    • Mishal Hospital (<2km)
    • Anjali Hospital-ER (<2km)
    • Anjali Hospital (<2km)
    • Sai Taraksh Physiotherapy Clinic (<2km)
    • Ingle Pathology Lab (<2km)
  • Hotel

    • Om Sai Hotel (<1km)
    • Hotel Sai (<1km)
    • Capital O 37456 Arusai (<2km)
    • Pioneer Hotel (<2km)
    • Shri Charbhuja Hotel (<2km)
  • Shopping Centre

    • Go Colors-Elpro City Mall (<1km)
    • Laxmitara Market (<1km)
    • Shivaji Maharaj Market (<1km)
    • India (<2km)
    • Durga Selection (<2km)
    • Jyotirling Selection (<2km)
    • Padmavati Selection (<2km)
  • Recreation

    • River Garden (<1km)
    • PCMC Garden (<2km)
    • Strength Fitness Club (<2km)
  • Accommodation

    • Sarja Lodge (<2km)
  • Landmark/Attraction

    • Shivaji Statue (<2km)
    • Pune (<2km)
  • Business & Services

    • Chamunda Enterprises (<2km)
Project ID
J398869118
Updated
Searches
2863
Views
745