Elevation
Main Entrance
Side View
 22

Vijay Orovia - Waghbil, Thane

Builder
Vijay Group & Suraksha Realty
Construction
Completed
Completion
Mar, 2023
Properties
Apartments
RERA
P51700005653

Description

The land of prosperity

Vijay Orovia stands majestically in Wagbil area, Ghodbunder Road ,Thane West. It has 8 majestic towers souring 27 floors from the ground. He is offering luxurious 1,2,3 BHK apartments in this project. There will be a total of 1300 families living in this project once the project is completed. It is spread across 16 acres and is designed to be a gated residential complex.


Amenities
:-
  • Basement 1, Ground Podium, 1st Podium, Recreation floor at Stilt level + 27 Habitable floors.
  • Earthquake resistant RCC structure
  • Green building feature- IGBC Pre-certified Gold
  • Well planned vehicle-free recreation floor at stilt level attached to podium
  • Video door phone and intercom system
  • Vitrified tile flooring
  • Fire-fighting system, D.G. power back-up & Sewage treatment plant
  • Proposed Retail & Commercial Spaces
Amenities On Recreation Floor At Stilt Level Attached To The Podium
  • Games room with carom, chess, table tennis, pool table & cards.
  • The common room containing a mirror and wooden flooring for Yoga/ Meditation/ Aerobics & other activities.
  • Reading room.
  • Senior citizen’s area
  • Hobby room
Vijay Group was started in 1985 with an objective to develop and deliver the best homes. The group has developed more than 4 million sq feet spaces till now under residential and commercial segment. Vijay Group has a large footprint in Ghodbunder road developing gated residential communities. The group is known for quality constructions and transparency in its work. Vijay has a successfully completed more than 15 projects and has settled 5,000 happy families. Currently, the group is developing 6 projects in Ghodbunder road and more 2 projects are in the pipeline stage.

Highlights

  • Power Back-up
  • Visitor Parking
  • Maintenance Staff
  • Boring / Tube-well
  • Rain Water Harvesting
  • Waste Disposal
  • Centrally Air Conditioned
  • Lifts
  • RO System
  • Private Terrace
  • Balcony
  • Basement
  • Electronic Security
  • Park Facing
  • Woodwork
  • Modular Kitchen
  • Swimming Pool
  • Park
  • Club / Community Center
  • Cafeteria / Food Court
  • Conference room
  • Service / Goods Lift
  • Clear Title
  • Freehold Land
  • Plot Boundary Wall
  • Society Boundary Wall
  • Club / Community Center
  • Adjacent to Main Road
  • Water Connection
  • Electric Connection
  • Close to Hospital
  • Close to School
  • Close to Shopping Center/Mall

Configurations

Type Area Possession Price *
1BHK Apartment383 SqFeetImmediate/Ready to move₹ 68 lakhs
1BHK Apartment439 SqFeetImmediate/Ready to move₹ 78.2 lakhs
1BHK Apartment550 SqFeetImmediate/Ready to move₹ 84 lakhs
2BHK Apartment580 SqFeetImmediate/Ready to move₹ 1.08 crore
2BHK Apartment660 SqFeetImmediate/Ready to move₹ 99 lakhs
2BHK Apartment762 SqFeetImmediate/Ready to move₹ 1.32 crore
2BHK Apartment71.54 SqMetersImmediate/Ready to move₹ 1.05 crore
3BHK Apartment736 SqFeetImmediate/Ready to move₹ 1.22 crore
3BHK Apartment869 SqFeetImmediate/Ready to move₹ 1.5 crore
3BHK Apartment90.12 SqMetersImmediate/Ready to move₹ 1.85 crore
* Data has been collected from publicly available sources and may not be up to date.

RERA

P51700005653 OROVIA PHASE 1 Completed

Confirmed with MahaRERA on 21 Sep 2026. Registered as "OROVIA PHASE 1".

Promoter
VIJAY SURAKSHA REALTY LLP
Registered on
11 Aug 2017
Proposed completion
Mar 2023
Project type
Others
Planning authority
Others
Address as filed
Waghbil Road, Village Kavesar, Ghodbunder Road, Thane (M Corp.), Thane, Thane, 400607
Land area
4,083 sq m (43,950 sq ft)
Sanctioned built-up area
33,845 sq m (364,312 sq ft)
Buildings
IVY (32 floors); FERN (32 floors); PERIWINKLE (32 floors); INDIGO (32 floors); Marigold West End (4 floors); MARIGOLD East End (4 floors)
Parking
Open Space 0, Closed/Covered 708
Complaints on the portal
28
BuildingUnit typeCarpet areaUnits
IVY1BHK SPACIO 37 sq m (394 sq ft) 54
IVY1BHKSMART 36 sq m (384 sq ft) 54
IVY1 BHK SMART 36 sq m (383 sq ft) 49
FERN1 BHK SMART 36 sq m (384 sq ft) 54
FERN1 BHK SPACIO 37 sq m (394 sq ft) 54
FERN1 BHK SMART 36 sq m (383 sq ft) 49
PERIWINKLE2BHK SPACIO 56 sq m (601 sq ft) 49
PERIWINKLE2 BHK SMART 46 sq m (497 sq ft) 54
PERIWINKLE2BHK SPACIO 54 sq m (579 sq ft) 54
INDIGO3BHK 68 sq m (736 sq ft) 54
INDIGO2BHK LUXURY 61 sq m (653 sq ft) 27
INDIGO2.5BHK 64 sq m (693 sq ft) 54
INDIGO2BHK LUXURY 58 sq m (619 sq ft) 22
Marigold West EndOffice space 31 sq m (333 sq ft) 1
Marigold West EndSHOP 31 sq m (333 sq ft) 10
Marigold West EndOffice space 31 sq m (332 sq ft) 6
Marigold West EndOffice space 31 sq m (330 sq ft) 4
Marigold West EndOffice space 31 sq m (330 sq ft) 1
Marigold West EndRESTAURANT 55 sq m (588 sq ft) 2
Marigold West EndOffice space 35 sq m (372 sq ft) 1
Marigold West EndOffice space 31 sq m (332 sq ft) 1
Marigold West EndOffice space 23 sq m (247 sq ft) 1
Marigold West EndSHOP 28 sq m (298 sq ft) 1
Marigold West EndOffice space 24 sq m (258 sq ft) 1
Marigold West EndOffice space 28 sq m (297 sq ft) 1
Marigold West EndSHOP 35 sq m (372 sq ft) 1
Marigold West EndSHOP 31 sq m (332 sq ft) 1
Marigold West EndSHOP 27 sq m (290 sq ft) 1
Marigold West EndSHOP 24 sq m (257 sq ft) 1
Marigold West EndOffice space 27 sq m (289 sq ft) 1
Marigold West EndSHOP 23 sq m (248 sq ft) 1
MARIGOLD East EndOffice space 20 sq m (219 sq ft) 1
MARIGOLD East EndSHOP 104 sq m (1,116 sq ft) 1
MARIGOLD East EndSHOP 104 sq m (1,115 sq ft) 2
MARIGOLD East EndOffice space 31 sq m (331 sq ft) 1
MARIGOLD East EndOffice space 31 sq m (330 sq ft) 1
MARIGOLD East EndOffice space 31 sq m (330 sq ft) 2
MARIGOLD East EndSHOP 31 sq m (331 sq ft) 1
MARIGOLD East EndSHOP 20 sq m (216 sq ft) 1
MARIGOLD East EndSHOP 31 sq m (333 sq ft) 1
MARIGOLD East EndOffice space 31 sq m (332 sq ft) 3
MARIGOLD East EndOffice space 33 sq m (359 sq ft) 1
MARIGOLD East EndSHOP 31 sq m (332 sq ft) 1
MARIGOLD East EndSHOP 34 sq m (367 sq ft) 1
MARIGOLD East EndOffice space 35 sq m (373 sq ft) 1
MARIGOLD East EndOffice space 32 sq m (344 sq ft) 1
MARIGOLD East EndSHOP 32 sq m (339 sq ft) 1
MARIGOLD East EndOffice space 82 sq m (882 sq ft) 1
MARIGOLD East EndOffice space 104 sq m (1,116 sq ft) 3
MARIGOLD East EndSHOP 27 sq m (295 sq ft) 1
MARIGOLD East EndOffice space 31 sq m (334 sq ft) 1
MARIGOLD East EndRESTAURANT 55 sq m (588 sq ft) 2
MARIGOLD East EndOffice space 32 sq m (340 sq ft) 1
MARIGOLD East EndOffice space 32 sq m (343 sq ft) 1
MARIGOLD East EndOffice space 31 sq m (330 sq ft) 2
MARIGOLD East EndSHOP 32 sq m (346 sq ft) 1
MARIGOLD East EndSHOP 31 sq m (333 sq ft) 3
MARIGOLD East EndOffice space 27 sq m (295 sq ft) 1
MARIGOLD East EndOffice space 31 sq m (332 sq ft) 1
MARIGOLD East EndSHOP 31 sq m (333 sq ft) 6
MARIGOLD East EndSHOP 31 sq m (335 sq ft) 2
MARIGOLD East EndSHOP 82 sq m (879 sq ft) 1
MARIGOLD East EndSHOP 34 sq m (369 sq ft) 1
MARIGOLD East EndOffice space 31 sq m (330 sq ft) 1
MARIGOLD East EndOffice space 31 sq m (332 sq ft) 3
Construction progress as reported to the portal

IVY

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

FERN

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

PERIWINKLE

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

INDIGO

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Marigold West End

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

MARIGOLD East End

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Common areas and facilities

  • Internal Roads & Footpaths: 50% - SHARED BY ENTIRE LAYOUT
  • Water Supply: 100% - TO BE GIVEN BY MUNICIPAL CORPORATION AFTER OC
  • Sewerage (Chamber, Lines, Septic Tank , STP): 100% - STP TO BE GIVEN AS SHARED AMENITY AS APPROVED TMC
  • Storm Water Drains: 100% - TO BE GIVEN AS APPROVED BY TMC
  • Landscaping & Tree Planting: 100% - SHARED BY ENTIRE LAYOUT
  • Street Lighting: 20% - SHARED BY ENTIRE LAYOUT
  • Treatment And Disposal Of Sewage And Sullage Water: 100% - WATER SHALL BE USED FOR TOILET FLUSHING AND GARDEN
  • Solid Waste Management And Disposal: 100% - OWC SHALL BE PROVIDED & SHARED BY ENTIRE LAYOUT
  • Water conservation /Rain water harvesting: 100% - RWH PIT TO BE GIVEN AS APPROVED BY TMC
  • Energy managemcnt: 50% - ENERGY EFFICIENT LIGHTINGS & DG FOR COMMON AREA
  • Fire protection and fire safety requirements: 100% - AS PER CFO NOC
  • Electrical meter room, sub-station, receiving station: 60% - ELEC.METER ROOM PROPOSED & SUBSTAN SHARED BYLAYOUT
  • Aggregate area of recreational Open Space: 25% - RG WILL BE SHARED BY LAYOUT
  • OTHER COMMON AMENITIES LIKE COMMON ROOM WOODEN FLOORING GAMES ROOM READING ROOM SMALL AREA PARTY: 80% - SHARED BY ENTIRE LAYOUT
  • SOCIETY OFFICE: 100% - TO BE PROVIDED AS PER APPROVED PLAN BY MUNI. CORP.
RERA details are as filed by the promoter with the state authority and as read from its portal on the date shown; PropertyWala.com has not verified them independently.

Reviews

Be the first to write a review of Vijay Orovia and become a Project expert!
  • Post an informative review and get 1 additional basic property listing FREE of cost*.
  • Your review will be displayed prominently on your property listing page and other pages on the website.
  • For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
* The review must be factual, informative and unique.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of Vijay Orovia
Cons:
Enter some negative aspects of Vijay Orovia

Location

Vijay Orovia,Ghodbunder Road, Waghbil, Thane - 400615 (Maharashtra)

* Location may be approximate

Nearby

  • Transport

    • Hindustan Petroleum (~2 km)
    • Azad Nagar Bus Stop (~4 km)
    • ST Bus Stand - Khopat (~10 km)
    • Thane (~12 km)
    • Chhatrapati Shivaji Maharaj International Airport (~31 km)
    • Navi Mumbai International Airport (~44 km)
  • Shopping & Dining

    • Haldiram's (<1 km)
    • Cafe Coffee Day (~1 km)
    • Dmart (~2 km)
    • Panchvati Sweets (~2 km)
    • Big Centre (~2 km)
    • Amrapali Arcade (~7 km)
  • Healthcare

    • Neeta Ambani Hospital (<1 km)
    • Genericart Medicine Store (~1 km)
    • Wellness Forever (~1 km)
    • Healing Hands Clinic - Thane West (~2 km)
    • Manasi Maternity & General Hospital (~2 km)
    • Shiv Drushti Eye & Dental Hospital Clinic (~2 km)
  • Education

    • Hiranandani Foundation School (~1 km)
    • New Horizon Scholar's School (Rodas) (~2 km)
    • AP shah Institute of Technology (~2 km)
    • Shubham Raje (~2 km)
    • The Indian Library (~8 km)
    • Industrial Training Institute (ITI) (~13 km)
  • Leisure & Entertainment

    • Westview Park (<1 km)
    • Racquet Club (~1 km)
    • Inox (~10 km)
    • Dadoji Konddev Stadium (~11 km)
    • Tiger & Lion Safari (~16 km)
    • Kharghar Valley Golf Course (~34 km)
  • Services

    • UCO Bank (~1 km)
    • Mumbai- Thane Godhbunder Branch ATM (~2 km)
    • DHL (~4 km)
    • Rabodi Police Station (~8 km)
    • Rustomjee Fire Station (~9 km)
    • Thane Municipal Corporation (~10 km)
  • Religious Places

    • Ganesh Mandir (~2 km)
    • ganesh temple (~3 km)
  • Business & Hospitality

    • Colour Chem (~7 km)
    • Raymond Mills (~9 km)
    • ibis Thane (~9 km)
    • IBIS (~9 km)
    • Ashar IT Park (~11 km)
    • Reliance Corporate Park (~22 km)
Places © OpenStreetMap contributors, Overture Maps Foundation
Project ID
J751190254
Updated
Searches
7181
Views
3602