Shubh Gateway - Viman Nagar, Pune
- Builder
- Shubh Landmarks
- Construction
- Under Construction
- Completion
- Dec, 2026
- Properties
- Apartments, Residential Lands
- RERA
- P52100018200
Description
Reflects beauty in its true sense
Shubh Gateway by Shubh Landmarks is offering spacious 2, 3 and 4 bhk apartments in the size ranges in between 970 to 1424 sqft. There are some unique facilities such as Rain Water Harvesting, Multipurpose Courts, Fire Fighting Equipment present in the project. Apart from the location and connectivity advantages, the project also offers an impressive state of social infrastructure. There are several schools, colleges, grocery stores, banks and ATMs available in the immediate vicinity.- Gymnasium
- Children's play area
- Club House
- Intercom
- Power Backup
- Lift Available
- CCTV
- 24 X 7 Security
- Indoor Games
- Car Parking
- Multipurpose Room
- Rain Water Harvesting
- 24 Hours Water Supply
Highlights
- Power Back-up
- Visitor Parking
- Maintenance Staff
- Water Supply / Storage
- Rain Water Harvesting
- Lifts
- High Speed Internet
- Security Guards
- Intercom Facility
- Balcony
- Reserved Parking
- Swimming Pool
- Park
- Fitness Centre / GYM
- Club / Community Center
Configurations
| Type | Area | Possession | Price * |
|---|---|---|---|
| 2BHK Apartment | 970 SqFeet | Within 3 Months | ₹ 72.72 lakhs |
| 3BHK Apartment | 1,155 SqFeet | Within 3 Months | ₹ 86.59 lakhs |
| 4BHK Apartment | 1,424 SqFeet | Within 3 Months | ₹ 1.07 crore |
| Residential Land | 1,500 SqFeet | Within 3 Months | ₹ 4.5 lakhs |
RERA
P52100018200 SHUBH GATEWAY Active 43% built
Confirmed with MahaRERA on 22 Sep 2026. Registered as "SHUBH GATEWAY".
- Promoter
- Shubh Landmarks
- Registered on
- 15 Oct 2018
- Proposed completion
- Dec 2026
- Project type
- Residential / Group Housing
- Planning authority
- Others
- Address as filed
- Airport Road, Vimannagar, LOHGAON, Haveli, Pune, 411032
- Land area
- 8,830 sq m (95,048 sq ft)
- Sanctioned built-up area
- 8,247 sq m (88,777 sq ft)
- Buildings
- A Wing (15 floors) - 2 of 110 available; B Wing (15 floors) - 0 of 78 available; C Wing (15 floors) - 0 of 64 available; D Wing (15 floors) - 0 of 66 available
- Parking
- Open Space 0, Closed/Covered 280
| Building | Unit type | Carpet area | Units |
|---|---|---|---|
| A Wing | Shop | 36 sq m (384 sq ft) | 1 |
| A Wing | 2BHK | 71 sq m (764 sq ft) | 1 |
| A Wing | 2BHK | 72 sq m (775 sq ft) | 11 |
| A Wing | 2BHK | 73 sq m (789 sq ft) | 1 |
| A Wing | 3BHK | 94 sq m (1,017 sq ft) | 29 |
| A Wing | 3BHK | 103 sq m (1,109 sq ft) | 11 |
| A Wing | 4BHK | 119 sq m (1,286 sq ft) | 11 |
| A Wing | Shop | 53 sq m (574 sq ft) | 2 |
| A Wing | Shop | 43 sq m (461 sq ft) | 1 |
| A Wing | Shop | 41 sq m (442 sq ft) | 6 |
| A Wing | Shop | 64 sq m (689 sq ft) | 2 |
| A Wing | Shop | 34 sq m (368 sq ft) | 6 |
| B Wing | Shop | 34 sq m (368 sq ft) | 4 |
| B Wing | Shop | 33 sq m (354 sq ft) | 3 |
| B Wing | Shop | 56 sq m (607 sq ft) | 1 |
| B Wing | Shop | 53 sq m (574 sq ft) | 2 |
| B Wing | Shop | 51 sq m (551 sq ft) | 1 |
| B Wing | Shop | 48 sq m (521 sq ft) | 1 |
| B Wing | Shop | 46 sq m (499 sq ft) | 1 |
| B Wing | Shop | 46 sq m (492 sq ft) | 1 |
| B Wing | Shop | 41 sq m (442 sq ft) | 4 |
| B Wing | Shop | 40 sq m (436 sq ft) | 1 |
| B Wing | Shop | 39 sq m (416 sq ft) | 1 |
| B Wing | Shop | 26 sq m (280 sq ft) | 3 |
| B Wing | Shop | 38 sq m (412 sq ft) | 1 |
| B Wing | 2BHK | 72 sq m (775 sq ft) | 10 |
| B Wing | 2BHK | 73 sq m (789 sq ft) | 1 |
| B Wing | 3BHK | 94 sq m (1,017 sq ft) | 29 |
| B Wing | 3BHK | 103 sq m (1,109 sq ft) | 10 |
| B Wing | 4BHK | 119 sq m (1,286 sq ft) | 11 |
| B Wing | 2BHK | 71 sq m (764 sq ft) | 1 |
| B Wing | Shop | 75 sq m (809 sq ft) | 1 |
| B Wing | Shop | 64 sq m (689 sq ft) | 2 |
| B Wing | Shop | 32 sq m (342 sq ft) | 1 |
| C Wing | Shop | 33 sq m (354 sq ft) | 3 |
| C Wing | 2BHK | 72 sq m (775 sq ft) | 10 |
| C Wing | Shop | 45 sq m (485 sq ft) | 2 |
| C Wing | Shop | 37 sq m (398 sq ft) | 1 |
| C Wing | 3BHK | 103 sq m (1,109 sq ft) | 10 |
| C Wing | Shop | 40 sq m (436 sq ft) | 1 |
| C Wing | Shop | 48 sq m (521 sq ft) | 1 |
| C Wing | 2BHK | 73 sq m (789 sq ft) | 1 |
| C Wing | Shop | 39 sq m (416 sq ft) | 1 |
| C Wing | 2BHK | 71 sq m (764 sq ft) | 1 |
| C Wing | Shop | 38 sq m (412 sq ft) | 1 |
| C Wing | Shop | 26 sq m (280 sq ft) | 3 |
| C Wing | 4BHK | 119 sq m (1,286 sq ft) | 11 |
| C Wing | Shop | 32 sq m (342 sq ft) | 1 |
| C Wing | 3BHK | 95 sq m (1,019 sq ft) | 1 |
| C Wing | 3BHK | 94 sq m (1,017 sq ft) | 29 |
| C Wing | Shop | 37 sq m (399 sq ft) | 1 |
| C Wing | 2BHK | 77 sq m (831 sq ft) | 1 |
| C Wing | Shop | 51 sq m (551 sq ft) | 1 |
| D Wing | 2BHK | 71 sq m (764 sq ft) | 1 |
| D Wing | 2BHK | 72 sq m (775 sq ft) | 11 |
| D Wing | 2BHK | 73 sq m (789 sq ft) | 1 |
| D Wing | 3BHK | 94 sq m (1,017 sq ft) | 30 |
| D Wing | 3BHK | 95 sq m (1,019 sq ft) | 1 |
| D Wing | 4BHK | 119 sq m (1,286 sq ft) | 11 |
| D Wing | 3BHK | 103 sq m (1,112 sq ft) | 1 |
| D Wing | 3BHK | 103 sq m (1,109 sq ft) | 10 |
| Quarterly return | Filed | Built | Units booked |
|---|---|---|---|
| Q3 FY 2018-2019 | 11 Aug 2026 | - | - |
| Q4 FY 2018-2019 | 11 Aug 2026 | - | - |
| Q1 FY 2019-2020 | 11 Aug 2026 | - | - |
| Q2 FY 2019-2020 | 11 Aug 2026 | - | - |
| Q3 FY 2019-2020 | 11 Aug 2026 | - | - |
| Q4 FY 2019-2020 | 11 Aug 2026 | - | - |
| Q1 FY 2020-2021 | 11 Aug 2026 | - | - |
| Q2 FY 2020-2021 | 11 Aug 2026 | - | - |
| Q3 FY 2020-2021 | 11 Aug 2026 | - | - |
| Q4 FY 2020-2021 | 11 Aug 2026 | - | - |
| Q1 FY 2021-2022 | 10 Aug 2026 | - | - |
| Q2 FY 2021-2022 | 10 Aug 2026 | - | - |
| Q3 FY 2021-2022 | 10 Aug 2026 | - | - |
| Q4 FY 2021-2022 | 10 Aug 2026 | - | - |
| Q1 FY 2022-2023 | 10 Aug 2026 | - | - |
| Q2 FY 2022-2023 | 10 Aug 2026 | - | - |
| Q3 FY 2022-2023 | 10 Aug 2026 | - | - |
| Q4 FY 2022-2023 | 10 Aug 2026 | - | - |
| Q1 FY 2023-2024 | 10 Aug 2026 | - | - |
| Q2 FY 2023-2024 | 10 Aug 2026 | - | - |
| Q3 FY 2023-2024 | 10 Aug 2026 | - | - |
| Q4 FY 2023-2024 | 10 Aug 2026 | - | - |
| Q1 FY 2024-2025 | 10 Aug 2026 | - | - |
| Q2 FY 2024-2025 | 10 Aug 2026 | - | - |
| Q3 FY 2024-2025 | 11 Aug 2026 | - | - |
| Q4 FY 2024-2025 | 11 Aug 2026 | - | - |
| Q1 FY 2025-2026 | 11 Aug 2026 | - | - |
| Q2 FY 2025-2026 | 11 Aug 2026 | - | - |
| Q3 FY 2025-2026 | 11 Aug 2026 | - | - |
| Q4 FY 2025-2026 | 11 Aug 2026 | - | - |
| Q1 FY 2026-2027 | 11 Aug 2026 | - | - |
Construction progress as reported to the portal
A Wing
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 0%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 0%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 0%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
B Wing
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 0%
- Plinth: 100%
- Stilt Floor: 0%
- Slabs of Super Structure: 0%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 0%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
C Wing
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 100%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 0%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
D Wing
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 100%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 0%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
Common areas and facilities
- Internal Roads & Footpaths: 0% - To be completed with project
- Water Supply: 0% - To be completed with project
- Sewerage (Chamber, Lines, Septic Tank , STP): 0% - To be completed with project
- Storm Water Drains: 0% - To be completed with project
- Landscaping & Tree Planting: 0% - To be completed with project
- Street Lighting: 0% - To be completed with project
- Community Buildings: 0% - To be completed with project
- Solid Waste Management And Disposal: 0% - To be completed with project
- Water conservation /Rain water harvesting: 0% - To be completed with project
- Energy managemcnt: 0% - To be completed with project
- Fire protection and fire safety requirements: 0% - To be completed with project
- Electrical meter room, sub-station, receiving station: 0% - To be completed with project
- Aggregate area of recreational Open Space: 0% - To be completed with project
Reviews
Be the first to write a review of Shubh Gateway and become a Project expert!
- Post an informative review and get 1 additional basic property listing FREE of cost*.
- Your review will be displayed prominently on your property listing page and other pages on the website.
- For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
Enter some positive aspects of Shubh Gateway
Enter some negative aspects of Shubh Gateway
News
Car falls from Shubh Gateway Apartment parking in Pune
Hindustan Times · · Residential
A car plummeted from first-floor parking at Shubh Gateway Apartment in Viman Nagar when a supporting wall collapsed; no injuries reported.
Key facts
A black car fell from the first-floor parking lot of Shubh Gateway Apartment in Viman Nagar on Sunday morning after a portion of the parking structure collapsed. CCTV footage shows the wall supporting the parking space giving way, with the vehicle tumbling backwards and crashing to the ground. A security guard witnessed the incident from a few meters away. No injuries were reported. Police are investigating the cause of the collapse. The driver may have miscalculated parking, with the force potentially causing the structural failure. Emergency services secured the area promptly.
Car Falls From Second Floor Parking At Shubh Gateway Pune
The Free Press Journal · · Residential
A car fell from the second-floor parking lot of Shubh Gateway apartment in Viman Nagar, Pune after a wall collapsed; no injuries reported.
Key facts
On Sunday morning, a car fell from the 2nd-floor parking lot of Shubh Gateway Apartment in Viman Nagar, Pune. CCTV footage showed a black four-wheeler parked on the second floor; the parking lot wall collapsed and the car slid backwards before falling to the ground. The driver may have miscalculated while parking and hit the wall, causing the collapse. No injuries were reported and no major property damage occurred. Emergency services reached the spot and secured the area.
Car falls from Shubh Gateway apartment parking structure
Deccan Chronicle · · Regulatory
A car fell from the first-floor parking lot at Shubh Gateway Apartment complex in Pune's Viman Nagar after structural failure, prompting investigation into construction quality.
Key facts
Incident occurred Sunday morning around 9 a.m. at Shubh Gateway Apartment in Viman Nagar. Car parked in first-floor designated space began moving unexpectedly before parking structure gave way; vehicle fell to ground. CCTV captured the car sliding backward and plunging. No injuries reported as owner not inside vehicle.
Emergency services called; local authorities launched investigation. Preliminary assessments suggest parking structure weakened due to poor construction quality or inadequate maintenance. Municipal corporation officials and structural engineers tasked with examining site to determine cause.
Residents reported visible cracks in other parts of parking lot indicating potential risks for further failures. Apartment management expressed regret and assured full cooperation with investigation. Management pledged urgent repairs and comprehensive structural audit of building.
Incident sparked social media discussions criticizing lack of oversight in construction and maintenance of residential buildings.
Location
Shubh Gateway, Viman Nagar, Pune - 411014 (Maharashtra)
Landmarks
ATM/Bank/Exchange
- Axis Bank (<0.5km)
- Axis Bank Atm (<0.5km)
- Axis Bank-Datta Mandir Road Wakad (<0.5km)
- State Bank of India (<0.5km)
- Vijaya Bank-Pune Airport (<0.5km)
- Bank of Baroda (<0.5km)
- India Post Payments Bank-Airport Sub Post Office (<1km)
- Bank of Maharashtra (<1km)
- Bank of Baroda-Viman Nagar (<1km)
- ICICI Bank (<1km)
Hostel
- Symbiosis Law School Symbiosis Girls Hostel (<0.5km)
- Symbiosis Law College Girls Hostel (<0.5km)
- Symbiosis Hostel (<0.5km)
- Kazi Mansi Puru Society (<0.5km)
- symbiosis Girls Hostel (<0.5km)
- Rohanmithilagirlshostel (<0.5km)
- Shri Sai Hostel (<0.5km)
- dhanlaxmi housing society (<1km)
- Kazi Mansion (<1km)
- Symbiosis Girls Hostel Roha Mithila Puru Society (<1km)
- North Saidutta pg (<1km)
Business & Services
- Sava Vet (<0.5km)
Hotel
- Rohan Mithila Building T (<0.5km)
- Cosmos Luxury Viman Nagar (<0.5km)
- Cwe Canteen (<0.5km)
- Niva Stays Paradise (<0.5km)
- Rohan Mithila H Building (<1km)
- Bougainvilla Service Apartment (<1km)
- DDPK Airport Hotel (<1km)
- Nivastays Paradise (<1km)
- Fabexpress DDPK Ajay Inn Pune Airport (<1km)
- Konark Campus W 2 (<1km)
- Oyo 49705 Golden Leaf Airport Hotel (<1km)
- P S Hospitality Services (<1km)
- Trunktales 1 (<1km)
- Trunktales 2 (<1km)
- Silver Crest Hotel Silver Cre (<1km)
Public Transport
- Pune International Gate No 1 (<0.5km)
- Pune International Gate No 2 (<0.5km)
- Pune International Gate No 3 (<0.5km)
- Pune International Gate No 4 (<0.5km)
- Pune International Gate No 5 (<0.5km)
- Pune International Airport Cargo (<1km)
- Pune International Airport (<1km)
- Gangapuram Mhada (<1km)
- Officers Mess (<1km)
- Central School (Khese) (<1km)
- Konark Nagar (<1km)
Landmark/Attraction
- Translines Luxury Cars Hire (<0.5km)
Taxi Stand
- Ola Pick Up-Pune International Airport (<1km)
- Uber Pick Up Zone-Pune International Airport (<1km)
- Ola Drop Off-Pune International Airport Departure (<1km)
- Uber Drop Off-Pune International Airport Departure (<1km)
Restaurant & Shops
- Ankush Traders (<1km)
- Clink Bar (<1km)
- Namo (<1km)
- Shree Shub Laxmi General Stores (<1km)
- Prince Super Shop (<1km)
- Diamond Super Shopee (<1km)
- Pavers England (Pune Airport) (<1km)
- Relay Bookstore (<1km)
- Sankars the Book People (<1km)
- Rba Shakes and Flakes (<1km)
- Mufti (<1km)
- Seasons Fashion Hub Pune (<1km)
- Daimond Super Shop (<1km)
- Pried Super Shop (<1km)
- Mukesh Super Market (<1km)
- Aashapura Stores (<1km)
- Naresh Super Market (<1km)
- Shiva Enterprises (<1km)
- S K General Stores (<1km)
- S.S. Fabrics Ladies Shopee (<1km)
- Jeevan Supermarket (<1km)
- Shree Supermarket (<1km)
- Laxmi Supermarket (<1km)
- Crazy Times (<1km)
- Mahadev Shoppe (<1km)
- Mamboz (<1km)
- Prince Super Shopee (<1km)
Shopping Centre
- Da Milano Italia (<1km)
- Relay (<1km)
- Ava (<1km)
- Weikfield Circle (<1km)
- Town Square Shopping Centre (<1km)
Hospitals & Clinics
- Aditya Birla Memorial Hospital Medical Room (<1km)
- Deep Clinic (<1km)
- Planet Medico (<1km)
- Shifa Clinic (<1km)
- Rida Health Care Clinic (<1km)
- Gokula Polyclinic (<1km)
- Prakash Holistic Health Care Center (<1km)
- Top Chiropractor In Pune - The Physio9 Clinic/ (<1km)
Recreation
- Cricket Ground (<1km)
- Sanjay Park (<1km)
- Tridhaara Institute of Kathak (<1km)
Accommodation
- Tribe Stays (<1km)
- Trunktales 2 (<1km)
- Project ID
- J118982371
- Updated
- Searches
- 7820
- Views
- 2189