Main Entrance
Elevation
Side View
 17

Paranjape Happiness Hub - Khed Shivapur, Pune

Builder
Paranjape Schemes Constructions Ltd
Construction
Completed
Completion
Mar, 2025
Properties
Apartments
RERA
P52100000303

Description

Luxurious homes with proper ventilation

Paranjape Happiness Hub by Paranjape Schemes Constructions Ltd is conveniently situated at Khed Shivapur, Pune. The project is spread over 203 - 868 sq.ft. comprising of 1 and 2 bhk apartments in various sizes. The project is well equipped with Clubhouse With Indoor Games Essential Goods Shop Vegetable Market Multipurpose Function Hall / Badminton Court Landscaped Garden With Children’s Play Area and nearby connectivity such as schools, hospitals, road connectivity etc.

Amenities:
  • Clubhouse With Indoor Games
  • Essential Goods Shop
  • Vegetable Market
  • Multipurpose Function Hall / Badminton Court
  • Landscaped Garden With Children’s Play Area
  • Generator Backup For Lift,
  • Water Pumps And Common Area
  • Spacious Community Hall
  • Children’s Play Area
  • Shuttle Bus
  • Quality School
  • 24 Hour Security
  • Senior Citizen's Park
Paranjape Schemes Constructions Ltd Success comes from the desire to do extraordinary things to reach beyond the status quo and relentlessly chase your dreams. At Paranjape we don’t just build homes but believe in creating a happy vibrant community. We have over 190 top of the line projects completed in the past 30 years with a strong presence in both Residential and Commercial sectors. We are pioneers in developing housing projects for senior citizens in the country, under our Athashri brand as we feel we understand seniors' needs. Hence, we aspire to deliver not just a home with construction of walls but a light of hope, dreams and the happiness of a family.

Highlights

  • Power Back-up
  • Maintenance Staff
  • Rain Water Harvesting
  • Lifts
  • Security Guards
  • Fire Alarm
  • Reserved Parking
  • Swimming Pool
  • Park
  • Fitness Centre / GYM
  • Club / Community Center
  • Club / Community Center
  • Water Connection
  • Electric Connection
  • Close to Hospital
  • Close to School
  • Close to Shopping Center/Mall

Configurations

Type Area Possession Price *
1BHK Apartment544 SqFeetImmediate/Ready to move₹ 13 lakhs
2BHK Apartment868 SqFeetImmediate/Ready to move₹ 53 lakhs
* Data has been collected from publicly available sources and may not be up to date.

RERA

P52100000303 Happiness Hub - Varve Completed

Confirmed with MahaRERA on 22 Sep 2026. Registered as "Happiness Hub - Varve".

Promoter
PARANJAPE SCHEMES (CONSTRUCTION) LTD
Registered on
15 Jul 2017
Proposed completion
Mar 2025 (originally Mar 2020)
Project type
Residential / Group Housing
Planning authority
Others
Address as filed
Mumbai Bangalore Highway, Varve, Varve Kh., Bhor, Pune, 412206
Land area
49,929 sq m (537,449 sq ft)
Sanctioned built-up area
49,039 sq m (527,867 sq ft)
Buildings
A (13 floors); F (13 floors); G (13 floors); H (13 floors); I (13 floors); J (13 floors); K (13 floors); L (13 floors); M (13 floors); O (13 floors); P (13 floors); Q (13 floors); R (13 floors)
Parking
Open Space 116, Closed/Covered 208
Complaints on the portal
22
BuildingUnit typeCarpet areaUnits
A2BHK 41 sq m (443 sq ft) 2
A2BHK 41 sq m (443 sq ft) 5
A2BHK 41 sq m (443 sq ft) 1
A1BHK 27 sq m (288 sq ft) 20
ADEPARTMENTAL STORE 28 sq m (300 sq ft) 2
ADEPARTMENTAL STORE 40 sq m (434 sq ft) 1
A2BHK 41 sq m (443 sq ft) 2
A2BHK 41 sq m (443 sq ft) 32
F1BHK 27 sq m (288 sq ft) 1
F2BHK 40 sq m (435 sq ft) 1
F2BHK 42 sq m (452 sq ft) 1
F1BHK 25 sq m (271 sq ft) 1
F1BHK 27 sq m (285 sq ft) 46
F1BHK 27 sq m (286 sq ft) 1
F2BHK 39 sq m (417 sq ft) 1
F2BHK 40 sq m (433 sq ft) 1
F2BHK 40 sq m (434 sq ft) 10
F2BHK 40 sq m (435 sq ft) 10
F2BHK 40 sq m (435 sq ft) 1
F2BHK 42 sq m (451 sq ft) 1
F2BHK 42 sq m (451 sq ft) 10
F2BHK 42 sq m (453 sq ft) 9
F2BHK 42 sq m (453 sq ft) 1
G1BHK 27 sq m (286 sq ft) 1
G1BHK 27 sq m (288 sq ft) 1
G2BHK 40 sq m (431 sq ft) 1
G2BHK 40 sq m (431 sq ft) 1
G2BHK 41 sq m (441 sq ft) 1
G2BHK 41 sq m (442 sq ft) 11
G2BHK 41 sq m (443 sq ft) 11
G2BHK 43 sq m (460 sq ft) 10
G2BHK 43 sq m (461 sq ft) 6
G2BHK 43 sq m (461 sq ft) 5
G1BHK 27 sq m (285 sq ft) 24
H1RK 19 sq m (202 sq ft) 5
H1RK 19 sq m (202 sq ft) 18
H1RK 19 sq m (204 sq ft) 24
H1BHK 25 sq m (264 sq ft) 24
H1BHK 25 sq m (265 sq ft) 24
I1RK 19 sq m (202 sq ft) 23
I1RK 19 sq m (204 sq ft) 24
I1BHK 25 sq m (264 sq ft) 12
I1BHK 25 sq m (264 sq ft) 12
I1BHK 25 sq m (265 sq ft) 24
J1RK 19 sq m (202 sq ft) 12
J1RK 19 sq m (202 sq ft) 11
J1RK 19 sq m (204 sq ft) 24
J1BHK 24 sq m (264 sq ft) 6
J1BHK 25 sq m (264 sq ft) 18
J1BHK 25 sq m (265 sq ft) 12
J1BHK 25 sq m (265 sq ft) 12
K1RK 19 sq m (202 sq ft) 23
K1RK 19 sq m (204 sq ft) 24
K1BHK 25 sq m (264 sq ft) 12
K1BHK 25 sq m (265 sq ft) 24
K1BHK 25 sq m (264 sq ft) 12
L1BHK 25 sq m (264 sq ft) 12
L1RK 19 sq m (202 sq ft) 23
L1RK 19 sq m (204 sq ft) 24
L1BHK 25 sq m (264 sq ft) 12
L1BHK 25 sq m (265 sq ft) 24
M1BHK 27 sq m (285 sq ft) 35
M2BHK 40 sq m (426 sq ft) 6
M2BHK 40 sq m (434 sq ft) 24
M2BHK 41 sq m (438 sq ft) 18
M1BHK 27 sq m (285 sq ft) 12
O2BHK 38 sq m (414 sq ft) 2
O1BHK 27 sq m (288 sq ft) 1
O1BHK 27 sq m (286 sq ft) 1
O2BHK 40 sq m (434 sq ft) 5
O2BHK 42 sq m (453 sq ft) 1
O1BHK 26 sq m (285 sq ft) 6
O1BHK 26 sq m (285 sq ft) 5
O1BHK 27 sq m (285 sq ft) 36
O2BHK 40 sq m (433 sq ft) 11
O2BHK 40 sq m (434 sq ft) 6
O2BHK 42 sq m (453 sq ft) 10
O2BHK 42 sq m (451 sq ft) 11
P2BHK 40 sq m (433 sq ft) 1
P2BHK 40 sq m (434 sq ft) 5
P2BHK 42 sq m (451 sq ft) 1
P1BHK 27 sq m (286 sq ft) 1
P1BHK 27 sq m (288 sq ft) 1
P2BHK 38 sq m (411 sq ft) 1
P2BHK 42 sq m (450 sq ft) 1
P1BHK 28 sq m (300 sq ft) 3
P1BHK 28 sq m (301 sq ft) 23
P2BHK 38 sq m (412 sq ft) 1
P2BHK 39 sq m (423 sq ft) 11
P2BHK 40 sq m (434 sq ft) 5
P2BHK 42 sq m (450 sq ft) 10
P1BHK 28 sq m (300 sq ft) 19
P2BHK 42 sq m (452 sq ft) 10
Q1BHK 27 sq m (286 sq ft) 1
Q2BHK 42 sq m (450 sq ft) 1
Q2BHK 38 sq m (411 sq ft) 1
Q2BHK 40 sq m (433 sq ft) 1
Q2BHK 42 sq m (451 sq ft) 1
Q1BHK 27 sq m (288 sq ft) 1
Q1BHK 28 sq m (300 sq ft) 19
Q1BHK 28 sq m (300 sq ft) 3
Q1BHK 28 sq m (301 sq ft) 25
Q2BHK 38 sq m (412 sq ft) 1
Q2BHK 39 sq m (423 sq ft) 11
Q2BHK 40 sq m (434 sq ft) 5
Q2BHK 40 sq m (434 sq ft) 5
Q2BHK 42 sq m (450 sq ft) 10
Q2BHK 42 sq m (452 sq ft) 11
R2BHK 39 sq m (423 sq ft) 11
R2BHK 38 sq m (412 sq ft) 1
R2BHK 42 sq m (450 sq ft) 1
R1BHK 27 sq m (286 sq ft) 1
R2BHK 38 sq m (411 sq ft) 1
R1BHK 27 sq m (288 sq ft) 1
R1BHK 28 sq m (300 sq ft) 19
R1BHK 28 sq m (300 sq ft) 3
R1BHK 28 sq m (301 sq ft) 25
R2BHK 40 sq m (433 sq ft) 1
R2BHK 40 sq m (434 sq ft) 5
R2BHK 40 sq m (434 sq ft) 5
R2BHK 42 sq m (450 sq ft) 10
R2BHK 42 sq m (451 sq ft) 1
R2BHK 42 sq m (452 sq ft) 10
Quarterly returnFiledBuiltUnits booked
Q2 FY 2024-2025 not filed - in default - -
Q3 FY 2024-2025 not filed - in default - -
Q4 FY 2024-2025 not filed - in default - -
Construction progress as reported to the portal

A

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 85%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 98%

F

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 95%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 97%
  • Sanitary Fittings within the flats / premises: 97%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 97%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 97%

G

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 97%
  • Sanitary Fittings within the flats / premises: 97%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 97%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 97%

H

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 97%
  • Sanitary Fittings within the flats / premises: 97%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 97%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 97%

I

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 98%

J

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 95%
  • Sanitary Fittings within the flats / premises: 60%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 90%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 70%

K

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 98%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 98%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 98%

L

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 98%
  • Sanitary Fittings within the flats / premises: 75%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 90%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 80%

M

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 98%
  • Sanitary Fittings within the flats / premises: 98%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 99%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

O

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 90%
  • Sanitary Fittings within the flats / premises: 75%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 90%

P

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Q

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 90%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 95%

R

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 95%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Common areas and facilities

  • Internal Roads & Footpaths: 100% - -
  • Water Supply: 100% - -
  • Sewerage (Chamber, Lines, Septic Tank , STP): 100% - STP /CHAMBER LINE
  • Storm Water Drains: 100% - -
  • Landscaping & Tree Planting: 98% - -
  • Street Lighting: 100% - -
  • Treatment And Disposal Of Sewage And Sullage Water: 100% - -
  • Solid Waste Management And Disposal: 100% - -
  • Water conservation /Rain water harvesting: 100% - -
  • Energy managemcnt: 95% - solar water heating system
  • Fire protection and fire safety requirements: 100% - -
  • Electrical meter room, sub-station, receiving station: 100% - LT Room Substation Electrical Meter Room
  • Aggregate area of recreational Open Space: 90% - -
  • Open Parking: 100% - -
  • CLUB HOUSE: 100% - -
RERA details are as filed by the promoter with the state authority and as read from its portal on the date shown; PropertyWala.com has not verified them independently.

Reviews

Be the first to write a review of Paranjape Happiness Hub and become a Project expert!
  • Post an informative review and get 1 additional basic property listing FREE of cost*.
  • Your review will be displayed prominently on your property listing page and other pages on the website.
  • For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
* The review must be factual, informative and unique.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of Paranjape Happiness Hub
Cons:
Enter some negative aspects of Paranjape Happiness Hub

Location

Paranjape Happiness Hub, Khed Shivapur, Pune - 412205 (Maharashtra)

* Location may be approximate

Landmarks

  • Petrol Station

    • Reliance (<0.5km)
    • Indian Oil (<0.5km)
    • Bharat Petroleum (<0.5km)
    • Bharat Petroleum Corporation (<1km)
    • Hindustan Petroleum (<1km)
    • Shell (<2km)
    • B. P Kelwade (<4km)
  • Restaurant & Shops

    • Omkar Stationery and Mobile Recharge (<0.5km)
    • Balaji Super Market (<1km)
    • Shri Datt Provision Store (<1km)
    • Hotel Natraj (<1km)
    • Kamaldeep General Stores (<1km)
    • Sunil Beer Shop (<1km)
    • Narendra General Store (<1km)
    • Hotel Jeevan (<1km)
    • Jai Santoshi Mata General Stores (<1km)
    • Janta Kirana Stores (<1km)
    • Shri Jyotiba General Store (<1km)
    • Varsha Rani Cloth Centre (<2km)
    • Kuubera Factory Outlet (<2km)
    • Chintamani Arts (<2km)
    • Omkar Provision Stores & Stationery (<3km)
    • New Sansar General Stores (<3km)
    • Prasad Shoes (<3km)
    • Hotel Rohit (<3km)
    • Hotel Swagat (<4km)
    • Prasiddhi Collection (<5km)
    • Ice Cream Station (<6km)
    • Shri Gajanan Provision Store (<6km)
    • Jijau Book Sales & Stationers (<6km)
    • Sarvadnya Collection (<6km)
    • Jijau Book Depot (<6km)
    • Anjali Gift Articles (<6km)
    • Hotel Baneshwar Snacks Center (<6km)
    • Gurukrupa Cloth Center (<6km)
    • New Ramdev Cloth Center (<7km)
    • Shri Style Mens (<7km)
    • Gayatri Furniture General Store & Gift Articles (<7km)
    • Advait Traders (<7km)
    • Rajgad Collection (<7km)
    • Moraya Kirana & General Store (<7km)
  • Public Transport

    • Kalubai Mandir Bus Stop (<0.5km)
    • Shivanand Enclave Company (<1km)
    • Shriram Energy Company (<1km)
    • Varve 1 Bus Stop (<1km)
    • Kanjale Bus Stop (<3km)
    • Salavade Bus Stop (<4km)
    • Pravin Masala Company (<4km)
    • Shivregoan Phata (<4km)
    • Naygaon Bus Stop (<5km)
    • Khopi Bus Stop (<5km)
    • Poolachi Wadi (<6km)
    • Dalvi Vasti Bus Stop (<6km)
    • Cheladi Fata Bus Stop (<6km)
    • Kopo Phata/Bormal (<6km)
  • Hotel

    • Hotel Jagat Bhari-Kolhapur (<1km)
    • Hotel Nilkamal Pure Veg (<1km)
    • Rajgad Water Park & Resort (<1km)
    • Hotel Jeevan (<1km)
    • Vishal
    • Hotel Rajgad Palace-Kelawade (<2km)
    • Prathamesh Resorts-Diveagar (<2km)
    • Hotel Krushna Lodging (<3km)
    • Hotel Rohit-Kelawade (<3km)
    • Prathamesh Resorts (<4km)
    • Oyo 77133 Shri Trupti Lodging (<4km)
    • Vithal Kamat (<4km)
    • Oyo Hotel Trupti (<4km)
    • Hotel Omkar (<5km)
    • Shivraj Lodging (<6km)
    • Hotel Sai Sharddha (<6km)
    • Hotel Shiv Malhar (<7km)
  • Recreation

    • Rajgad Water Park & Adventure Park (<1km)
    • Prathamesh Resorts (<2km)
    • Bhor Baal Kendra (<6km)
    • Baneahwar van Udyan (<6km)
  • Hospitals & Clinics

    • Dawakhana (<1km)
    • Degaon Primary Heallth Sub Centre (<5km)
    • Siddhi Vinayak Hospital (<6km)
    • Siddhi Vinayak Hospital-ER (<6km)
    • Jagtap Ayurvedic Dawakhana (<6km)
    • Om Diagnostic Centre (<7km)
    • Nisarg Upchar Kendra (<7km)
  • ATM/Bank/Exchange

    • Pune District Central Co-Operative Bank-Shivre (<3km)
    • Bhor Krishi Bank (<6km)
    • Siddhivinayak Cooperative Credit Society (<6km)
    • Indicash Atm (<6km)
    • Pune Urban Bank-Khedshivapur (<7km)
    • Bank of Maharashtra (<7km)
    • Ramrajya Sahakari Bank (<7km)
  • Accommodation

    • Hotels Rajgad and Lodging (<4km)
  • Camping

    • Teakwood Camping (<6km)
Project ID
J289488111
Updated
Searches
2720
Views
1674