Metro Satyam Queens Necklace - Kharghar, Navi Mumbai
- Builder
- Satyam Developers
- Construction
- Under Construction
- Completion
- Apr, 2030
- Properties
- Apartments
- RERA
- P52000053533
Description
Double-height 5-star themed entrance lobby
Metro Satyam Queens Necklace is located in the heart of Kharghar, Navi Mumbai offers 1&2 BHK apartments ranging from 493-678 sqft. The project is spread over 4.5 acres of land. It consists of 4 towers with 25 floors and 624 units. The use of cutting-edge aluminum formwork in construction not only assures quality but also highlights the innovative spirit defining this development.Amenities
- Swimming Pool
- Library
- Multi-Purpose Hall
- Gymnasium
- Indoor Games
- Green Lawn
Satyam Developers is a renowned real estate brand in Navi Mumbai, known for building innovative residential and commercial projects. They have a strong team, decades of experience, and a commitment to customer satisfaction and quality. They have developed over a million square feet of properties in Navi Mumbai and have received awards for their excellence in construction quality.
Highlights
- Power Back-up
- Visitor Parking
- Maintenance Staff
- Water Supply / Storage
- Rain Water Harvesting
- Centrally Air Conditioned
- Lifts
- Security Guards
- Electronic Security
- Intercom Facility
- Balcony
- Modular Kitchen
- Swimming Pool
- Park
- Fitness Centre / GYM
- Club / Community Center
Configurations
| Type | Area | Possession | Price * |
|---|---|---|---|
| 1BHK Apartment | 404 SqFeet | Within 4 Years | ₹ 49.9 lakhs |
| 1BHK Apartment | 610 SqFeet | Within 4 Years | ₹ 57.9 lakhs |
| 1BHK Apartment | 750 SqFeet | Within 4 Years | ₹ 69 lakhs |
| 2BHK Apartment | 678 SqFeet | Within 4 Years | ₹ 82 lakhs |
| 2BHK Apartment | 950 SqFeet | Within 4 Years | ₹ 85 lakhs |
| 2BHK Apartment | 1,040 SqFeet | Within 4 Years | ₹ 95 lakhs |
RERA
P52000053533 Metro Satyam Queens Necklace Active 45% built
Confirmed with MahaRERA on 20 Sep 2026. Registered as "Metro Satyam Queens Necklace".
- Promoter
- Metrosatyam Builders LLP
- Registered on
- 10 Nov 2023
- Proposed completion
- Apr 2030 (originally Dec 2029)
- Project type
- Residential / Group Housing
- Planning authority
- Others
- Address as filed
- NH14, Rohinjan, Rohinjan, Panvel, Raigarh, 410208
- Land area
- 16,910 sq m (182,024 sq ft)
- Sanctioned built-up area
- 41,433 sq m (446,001 sq ft)
- Buildings
- Tower A (26 floors) - 18 of 148 available; Tower B (26 floors) - 16 of 140 available; Tower C (26 floors) - 32 of 140 available; Tower D (26 floors) - 38 of 148 available; Tower E (23 floors) - 55 of 149 available
- Parking
- Open Space 0, Closed/Covered 1646
| Building | Unit type | Carpet area | Units |
|---|---|---|---|
| Tower A | 1BHK | 36 sq m (382 sq ft) | 40 |
| Tower A | 1BHK | 41 sq m (443 sq ft) | 56 |
| Tower A | 2BHK | 53 sq m (570 sq ft) | 40 |
| Tower A | 2BHK | 59 sq m (632 sq ft) | 20 |
| Tower B | 1BHK | 36 sq m (382 sq ft) | 40 |
| Tower B | 1BHK | 41 sq m (443 sq ft) | 40 |
| Tower B | 2BHK | 53 sq m (570 sq ft) | 40 |
| Tower B | 2BHK | 59 sq m (632 sq ft) | 36 |
| Tower C | 1BHK | 36 sq m (382 sq ft) | 40 |
| Tower C | 1BHK | 41 sq m (443 sq ft) | 40 |
| Tower C | 2BHK | 53 sq m (570 sq ft) | 40 |
| Tower C | 2BHK | 59 sq m (632 sq ft) | 36 |
| Tower D | 1BHK | 36 sq m (382 sq ft) | 40 |
| Tower D | 1BHK | 41 sq m (443 sq ft) | 56 |
| Tower D | 2BHK | 53 sq m (570 sq ft) | 40 |
| Tower D | 2BHK | 59 sq m (632 sq ft) | 20 |
| Quarterly return | Filed | Built | Units booked |
|---|---|---|---|
| Q3 FY 2023-2024 | 4 Jun 2025 | - | - |
| Q4 FY 2023-2024 | 4 Jun 2025 | - | - |
| Q1 FY 2024-2025 | 11 Jun 2025 | - | - |
| Q2 FY 2024-2025 | 11 Jun 2025 | - | - |
| Q3 FY 2024-2025 | 11 Jun 2025 | - | - |
| Q4 FY 2024-2025 | 11 Jun 2025 | - | - |
| Q1 FY 2025-2026 | 25 Oct 2025 | - | - |
| Q2 FY 2025-2026 | 6 Feb 2026 | - | - |
| Q3 FY 2025-2026 | 15 Feb 2026 | - | - |
| Q4 FY 2025-2026 | 29 Apr 2026 | - | - |
| Q1 FY 2026-2027 | 25 Jul 2026 | - | - |
Construction progress as reported to the portal
Tower A
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 77%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 48%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 4%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 34%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
Tower B
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 83%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 67%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 12%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 45%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
Tower C
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 56%
- Plinth: 100%
- Stilt Floor: 56%
- Slabs of Super Structure: 90%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 28%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 59%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
Tower D
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 54%
- Plinth: 100%
- Stilt Floor: 54%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 34%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 56%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
Tower E
- Excavation: 100%
- Basement (if any): 0%
- Podiums (if any): 0%
- Plinth: 0%
- Stilt Floor: 0%
- Slabs of Super Structure: 0%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 0%
- Sanitary Fittings within the flats / premises: 0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 0%
Common areas and facilities
- Internal Roads & Footpaths: 0% - As per CC
- Water Supply: 0% - As per CC
- Sewerage (Chamber, Lines, Septic Tank , STP): 0% - As per CC
- Storm Water Drains: 0% - As per CC
- Landscaping & Tree Planting: 0% - As per CC
- Water conservation /Rain water harvesting: 50% - Only Rain Water Harvesting Tank to be made
- Fire protection and fire safety requirements: 0% - As per CC
- Electrical meter room, sub-station, receiving station: 0% - As per CC
- Aggregate area of recreational Open Space: 0% - As per CC
Reviews
Write a review
Be the first to write a review of Metro Satyam Queens Necklace and become a Project expert!
- Post an informative review and get 1 additional basic property listing FREE of cost*.
- Your review will be displayed prominently on your property listing page and other pages on the website.
- For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of Metro Satyam Queens Necklace
Enter some positive aspects of Metro Satyam Queens Necklace
Cons:
Enter some negative aspects of Metro Satyam Queens Necklace
Enter some negative aspects of Metro Satyam Queens Necklace
Location
Metro Satyam Queens Necklace, Kharghar, Navi Mumbai - 410208 (Maharashtra)
Nearby
-
Transport
- Reliance Petrol Pump (<1 km)
- Taloje Panchanand (~2 km)
- Sector-34 (~2 km)
- Belapur Bus Depot (~12 km)
- Navi Mumbai International Airport (~16 km)
- Chhatrapati Shivaji Maharaj International Airport (~32 km)
-
Shopping & Dining
- Gazebo Dhaba (<1 km)
- Ly's Cafe (~3 km)
- Kitchen Wold (~9 km)
- Little World Mall (~9 km)
- Glomax Mall (~9 km)
- APMC Fruit & Vegetable Market (~10 km)
-
Healthcare
- Jeevandeep Hospital (~2 km)
- Apex Multispeciality Hospital (~3 km)
- Bharat Medical (~3 km)
- Advanced Key Physiotherapy (~3 km)
- Sri Sai Clinic (~4 km)
- Zeelab Pharmacy (~4 km)
-
Education
- Empyrean School (~4 km)
- Ramsheth Thakur Public School (~6 km)
- Dhirubhai Ambani Knowledge City (~11 km)
- S.I.E.S College (~11 km)
- Cht.Sahu Maharaj Vachnalaya (~13 km)
- T.S. Chanakya Maritime University (~16 km)
-
Leisure & Entertainment
- Central Park (~5 km)
- Kharghar Valley Golf Course (~6 km)
- Maxus Cinema Hall (~7 km)
- Dr. DY Patil Sports Stadium (~11 km)
- Dr. DY Patil Sports Complex (~11 km)
- Butterfly Park (~11 km)
-
Services
- Axis Bank (~3 km)
- Bank of Baroda (~3 km)
- Panvel Muni Corp. Ward A Office (Kharghar Gram Panchayat) (~7 km)
- Tawa Delight (~8 km)
- chaitra cafe (~9 km)
- Kharghar Post Office (~9 km)
-
Religious Places
- Ganesh Temple (~3 km)
- Shri Swami Samartha math yogiraj yashwant maharaj (~4 km)
-
Business & Hospitality
- Aditya Birla Science and Technology Company (~6 km)
- Maharashtra Industrial Development Centre - MIDC Taloja (~7 km)
- Navi Mumbai Marriott Hotel (~10 km)
- Millennium Business Park, Mahape Village (~10 km)
- Courtyard by Marriott Navi Mumbai (~11 km)
- Reliance Corporate Park (~12 km)
- Project ID
- J326904119
- Updated
- Searches
- 2504
- Views
- 2036