Bringing about a lifestyle change is an important decision

Hill View Residency by Kumar Properties a residential development in Kothrud, Pune. The hillscape near Hillview Residency not only offers great panoramic views but also brings a breath of fresh air in to your home. The project is spread over 965 - 1200 sq.ft. comprising of 2 and 3 bhk apartments in various sizes. The project is equipped with below mentioned following amenities and nearby connectivity such as hospitals, railway station, schools and colleges etc.

Amenities :
  • 24Hrs Water Supply
  • CCTV Cameras
  • Club House
  • Covered Car Parking
  • Earthquake Resistant
  • Gym
  • Indoor Games
  • Landscaped Garden
  • Lift
  • Play Area
  • Security Personnel
  • 24Hrs Backup Electricity
The Kumar Properties Group is a well-diversified, value driven enterprise founded by Mr. K.H.Oswal on 15 August 1966.The group initially catered to the rental segment. In the ‘70s it progressed to construction of branded apartments. In the ‘80s it shifted to high-rise buildings and bungalow projects. In the ‘90s it pioneered luxurious, mega complexes. At the turn of the millennium, Kumar Properties diversified into IT parks and commercial buildings, With a strategic shift to large townships and commercial malls, the journey is far from over. In fact, it has just begun.

Highlights

  • Power Back-up
  • Visitor Parking
  • Maintenance Staff
  • Water Supply / Storage
  • Rain Water Harvesting
  • Lifts
  • Security Guards
  • Reserved Parking
  • Servant Quarter
  • Swimming Pool
  • Park
  • Fitness Centre / GYM
  • Club / Community Center
  • Club / Community Center
  • Park/Green Belt Facing
  • Water Connection
  • Electric Connection
  • Close to Hospital
  • Close to School
  • Close to Shopping Center/Mall

Configurations

Type Area Possession Price *
2BHK Apartment965 SqFeetImmediate/Ready to move-
2BHK Apartment1,020 SqFeetImmediate/Ready to move₹ 64 lakhs
3BHK Apartment1,200 SqFeetImmediate/Ready to move-
* Data has been collected from publicly available sources and may not be up to date.

RERA

P52100001962 HILLVIEW RESIDENCY PHASE I Completed

Confirmed with MahaRERA on 22 Sep 2026. Registered as "HILLVIEW RESIDENCY PHASE I".

Promoter
KUMAR BEHARAY PROPERTIES LLP
Registered on
31 Jul 2017
Proposed completion
May 2019
Project type
Residential / Group Housing
Planning authority
Others
Address as filed
D P ROAD, KOTHRUD, Pune (M Corp.), Pune City, Pune, 411038
Land area
9,919 sq m (106,775 sq ft)
Sanctioned built-up area
22,508 sq m (242,285 sq ft)
Buildings
J (17 floors); K (17 floors); L (17 floors); C (17 floors)
Parking
Open Space 47, Closed/Covered 297
Complaints on the portal
1
BuildingUnit typeCarpet areaUnits
J3BHK 104 sq m (1,120 sq ft) 5
J3BHK 107 sq m (1,148 sq ft) 5
J3BHK 107 sq m (1,151 sq ft) 8
J3BHK 104 sq m (1,123 sq ft) 8
J2BHK 85 sq m (912 sq ft) 2
J2BHK 87 sq m (938 sq ft) 2
J2BHK 72 sq m (771 sq ft) 30
K3BHK 104 sq m (1,123 sq ft) 8
K3BHK 107 sq m (1,148 sq ft) 5
K3BHK 104 sq m (1,120 sq ft) 5
K3BHK 107 sq m (1,151 sq ft) 8
K2BHK 72 sq m (771 sq ft) 30
K2 BHK 85 sq m (912 sq ft) 2
K2BHK 87 sq m (938 sq ft) 2
L2BHK 85 sq m (912 sq ft) 2
L3BHK 104 sq m (1,120 sq ft) 5
L3BHK 107 sq m (1,151 sq ft) 8
L2BHK 72 sq m (771 sq ft) 30
L3BHK 104 sq m (1,123 sq ft) 8
L2BHK 87 sq m (938 sq ft) 2
L3BHK 107 sq m (1,148 sq ft) 5
C2BHK 85 sq m (912 sq ft) 2
C3BHK 107 sq m (1,151 sq ft) 8
C2BHK 87 sq m (938 sq ft) 2
C3BHK 107 sq m (1,148 sq ft) 5
C3BHK 104 sq m (1,123 sq ft) 8
C2BHK 72 sq m (771 sq ft) 30
C3BHK 104 sq m (1,120 sq ft) 5
Construction progress as reported to the portal

J

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 100%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

K

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

L

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

C

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Common areas and facilities

  • Internal Roads & Footpaths: 40% - TAR ROAD
  • Water Supply: 75% - For 3 Bldgs (J
  • Sewerage (Chamber, Lines, Septic Tank , STP): 75% - K & L)
  • Storm Water Drains: 75% - For 3 Bldgs (J
  • Landscaping & Tree Planting: 40% - K
  • Street Lighting: 75% - L)
  • Treatment And Disposal Of Sewage And Sullage Water: 75% - For 3 Bldgs (J
  • Solid Waste Management And Disposal: 75% - K
  • Water conservation /Rain water harvesting: 75% - L)
  • Energy managemcnt: 75% - NA
  • Fire protection and fire safety requirements: 75% - For 3 Bldgs (J
  • Electrical meter room, sub-station, receiving station: 75% - K
  • Open Parking: 0% - For 3 Bldgs (J

P52100014848 HILL VIEW RESIDENCY PHASE I PROJECT II BUILDING A AND B Completed

Confirmed with MahaRERA on 22 Sep 2026. Registered as "HILL VIEW RESIDENCY PHASE I PROJECT II BUILDING A AND B".

Promoter
KUMAR BEHARAY PROPERTIES LLP
Registered on
8 Jan 2018
Proposed completion
Dec 2022
Project type
Residential / Group Housing
Planning authority
Others
Address as filed
D.P. ROAD, BEHIND MAHATMA SOCIETY KOTHRUD, Kothrud, Haveli, Pune, 411038
Land area
5,567 sq m (59,920 sq ft)
Sanctioned built-up area
11,254 sq m (121,143 sq ft)
Buildings
A (17 floors); B (17 floors)
Parking
Open Space 14, Closed/Covered 79
BuildingUnit typeCarpet areaUnits
A3BHK 107 sq m (1,151 sq ft) 8
A3 BHK 104 sq m (1,120 sq ft) 5
A2BHK 87 sq m (938 sq ft) 2
A3 BHK 107 sq m (1,148 sq ft) 5
A2BHK 85 sq m (912 sq ft) 2
A3 BHK 104 sq m (1,123 sq ft) 8
A2BHK 72 sq m (771 sq ft) 30
B3 BHK 104 sq m (1,120 sq ft) 5
B2 BHK 72 sq m (771 sq ft) 30
B3 BHK 104 sq m (1,123 sq ft) 8
B2 BHK 85 sq m (912 sq ft) 2
B3 BHK 107 sq m (1,151 sq ft) 8
B3 BHK 107 sq m (1,148 sq ft) 5
B2 BHK 87 sq m (938 sq ft) 2
Construction progress as reported to the portal

A

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

B

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Common areas and facilities

  • Internal Roads & Footpaths: 0% - -
  • Water Supply: 0% - -
  • Sewerage (Chamber, Lines, Septic Tank , STP): 0% - -
  • Storm Water Drains: 0% - -
  • Landscaping & Tree Planting: 0% - -
  • Street Lighting: 0% - -
  • Community Buildings: 0% - -
  • Treatment And Disposal Of Sewage And Sullage Water: 0% - -
  • Solid Waste Management And Disposal: 0% - -
  • Water conservation /Rain water harvesting: 0% - -
  • Energy managemcnt: 0% - -
  • Fire protection and fire safety requirements: 0% - -
  • Electrical meter room, sub-station, receiving station: 0% - -
  • Aggregate area of recreational Open Space: 0% - 0
  • Open Parking: 0% - -

P52100014885 HILLVEW RESIDENCY PHASE I PROJECT III BLDG N AND O Completed

Confirmed with MahaRERA on 22 Sep 2026. Registered as "HILLVEW RESIDENCY PHASE I PROJECT III BLDG N AND O".

Promoter
KUMAR BEHARAY PROPERTIES LLP
Registered on
9 Jan 2018
Proposed completion
Dec 2023
Project type
Residential / Group Housing
Planning authority
Others
Address as filed
D. P. ROAD, BEHIND MAHATMA SOCIETY KOTHRUD, Pune (M Corp.), Pune City, Pune, 411038
Land area
5,567 sq m (59,920 sq ft)
Sanctioned built-up area
11,254 sq m (121,143 sq ft)
Buildings
N (18 floors); O (18 floors)
Parking
Open Space 0, Closed/Covered 4
BuildingUnit typeCarpet areaUnits
N2 BHK 86 sq m (920 sq ft) 2
N2 BHK 71 sq m (759 sq ft) 16
N2 BHK 88 sq m (947 sq ft) 2
N3 BHK 104 sq m (1,118 sq ft) 5
N3 BHK 106 sq m (1,146 sq ft) 5
N3 BHK 107 sq m (1,150 sq ft) 8
N3 BHK 104 sq m (1,122 sq ft) 8
N2 BHK 71 sq m (759 sq ft) 14
O3 BHK 107 sq m (1,150 sq ft) 8
O3 BHK 104 sq m (1,122 sq ft) 8
O2 BHK 71 sq m (759 sq ft) 30
O3 BHK 106 sq m (1,146 sq ft) 5
O2 BHK 88 sq m (947 sq ft) 2
O2 BHK 86 sq m (920 sq ft) 2
O3 BHK 104 sq m (1,118 sq ft) 5
Construction progress as reported to the portal

N

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

O

  • Excavation: 100%
  • Basement (if any): 100%
  • Podiums (if any): 0%
  • Plinth: 100%
  • Stilt Floor: 100%
  • Slabs of Super Structure: 100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
  • Sanitary Fittings within the flats / premises: 100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%

Common areas and facilities

  • Internal Roads & Footpaths: 0% - -
  • Water Supply: 0% - -
  • Sewerage (Chamber, Lines, Septic Tank , STP): 0% - -
  • Storm Water Drains: 0% - -
  • Landscaping & Tree Planting: 0% - -
  • Street Lighting: 0% - -
  • Community Buildings: 0% - -
  • Treatment And Disposal Of Sewage And Sullage Water: 0% - -
  • Solid Waste Management And Disposal: 0% - -
  • Water conservation /Rain water harvesting: 0% - -
  • Energy managemcnt: 0% - -
  • Fire protection and fire safety requirements: 0% - -
  • Electrical meter room, sub-station, receiving station: 0% - -
  • Aggregate area of recreational Open Space: 0% - -
RERA details are as filed by the promoter with the state authority and as read from its portal on the date shown; PropertyWala.com has not verified them independently.

Reviews

Be the first to write a review of Hill View Residency and become a Project expert!
  • Post an informative review and get 1 additional basic property listing FREE of cost*.
  • Your review will be displayed prominently on your property listing page and other pages on the website.
  • For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
* The review must be factual, informative and unique.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of Hill View Residency
Cons:
Enter some negative aspects of Hill View Residency

Location

Hill View Residency, Kothrud, Pune - 411038 (Maharashtra)

* Location may be approximate

Landmarks

  • Recreation

    • Raj Mata Jijav Maa Sahab Udhyan (<0.5km)
    • Rohan Garden (<1km)
    • Shrinwas Gardens (<1km)
    • Saswad (<1km)
    • Municipal Park (<1km)
    • Limelight Event Planner (<1km)
  • Restaurant & Shops

    • Balaji Super Shoppee (<0.5km)
    • Prakash Super Market (<1km)
    • Sagar Super Shoppee (<1km)
    • Tejas Super Shoppee (<1km)
    • Dev Super Shoppe (<1km)
    • Hansita Boutique (<1km)
    • Siddhi Collection (<1km)
    • Pragati Super Shopee (<1km)
    • Bohemian (<1km)
    • Pancham Super Shoppe (<1km)
    • Rajlakshmi Super Market (<1km)
    • Denim Corner (<1km)
    • Laxmi Super Shopee (<1km)
    • Shri Ganesh Variety Stores (<1km)
    • Nikam for Men
    • Mayur Super Market (<1km)
    • Shree Ganesh Trading (<1km)
    • Kamal Super Market (<1km)
    • Mahadev Super Market (<1km)
    • City Girl (<1km)
    • Aashapura Trading Company (<1km)
    • Mayur Collection (<1km)
    • Om Enterprises (<1km)
    • Chandana Sarees (<1km)
    • Sadguru Collection (<1km)
    • Mahalaxmi Supermarket (<1km)
    • New Mahalaxmi Super Shopee (<1km)
    • Super Collections (<1km)
    • Goonj Design Studio (<1km)
    • Shreez Music (<1km)
    • Bhawani Grocery Store (<1km)
    • Guruprasad General Stores (<1km)
    • Dhanshree Trading (<1km)
    • Mahalakshmi Super Shopee (<1km)
  • Hospitals & Clinics

    • Armonia Homeopathic Consultant (<0.5km)
    • Yugantar Healthcare (<1km)
    • Dr. M Archana Kulkarni Clinic (<1km)
    • Maharaj Optical (<1km)
    • Doctor Rajashri Purohit Children Clinic (<1km)
    • Smile Forever Dental Care Clinic (<1km)
    • Dr Rohini Karpe (<1km)
    • Nisargopchar Clinic (<1km)
    • Nidan Ayurvedic Clinic (<1km)
    • Shri Vishvanil Clinic (<1km)
    • Netradip Eye Hospital-ER (<1km)
    • Netradip Eye Hospital (<1km)
    • Divya Drishti (<1km)
    • Oza Physiotherapy Clinic (<1km)
    • Satyam Pathology Lab (<1km)
    • Dr. Vipul Gandhi (<1km)
    • Garde Dental Clinic (<1km)
    • Dr. Swati Hendre Homeopathic Clinic (<1km)
    • No-1 Nurses Bureau (<1km)
    • Dr Rajashri Purohit (<1km)
    • Sarode Eyecare (<1km)
    • Kara Ayurved (<1km)
    • Priority Children
    • Machave Hospital-ER (<1km)
    • Machave Hospital (<1km)
    • Dr Sham Bhosale (<1km)
    • Perfect Smiles (<1km)
    • Gentle Dental Clinic (<1km)
    • Dr Abhijit Ashtaputre (<1km)
  • Public Transport

    • Karan Greens (<0.5km)
    • Kumbare Park (<1km)
    • Eklavya College (<1km)
    • Depot Left Bhush (<1km)
    • Futari Complex (<1km)
    • Atul Nagar Bus Stop (<1km)
    • Guruganesh Nagar (<1km)
  • Shopping Centre

    • Wonder Funkey Mall (<0.5km)
    • Megh Mall (<1km)
    • Shantiban Shopping Complex (<1km)
    • Mallik Mall (<1km)
  • ATM/Bank/Exchange

    • Cosmos Bank (<1km)
    • Bank of India (<1km)
    • Bank of India-Sahakar Nagar C&P Banking BR. (<1km)
    • Idbi Bank (<1km)
    • Axis Bank Atm (<1km)
    • Pradnyanand Apartments (<1km)
    • ICICI Bank (<1km)
    • Vrindawan Housing Society (<1km)
    • State Bank of India (<1km)
    • HDFC Bank (<1km)
    • Union Bank of India-Bavdhan (<1km)
  • Hotel

    • Hotel Shindeshahi (<1km)
    • Xcalibre Hospitality Services (<1km)
    • Oye Punjabi Hotel (<1km)
    • Chandni Lawn Hotel (<1km)
  • Hostel

    • Maitreya Plaza (<1km)
    • Chanakya Hostel (<1km)
    • Jalsa Hostel Chintamani Paradise (<1km)
Project ID
J811895472
Updated
Searches
6077
Views
1155