Bhairaav Goldcrest Residency Phase 2 - Ghansoli Sector-11, Navi Mumbai
- Builder
- Bhairaav Group
- Construction
- Under Construction
- Completion
- Mar, 2027
- Properties
- Apartments
- RERA
- P51700010579
Description
Effortless elegance and luxurious home
Bhairaav Goldcrest Residency Phase 2 by Bhairaav Group a residential development in Bhandup West, Mumbai. The project is spread over 693 - 1386 sq.ft. comprising of residential 1 and 2 bhk apartments in various sizes. The project is equipped with below mentioned following amenities and nearby connectivity such as hospitals, railway station,
Amenities :
- Amphitheater
- Basket Ball Court
- Carom Board
- CCTV Cameras
- Chess
- Club House
- Community Hall
- Covered Car Parking
- Gazebo
- Gym
- Health Facilities
- Indoor Games
- Jogging Track
- Landscaped Garden
- Lift
- Play Area
- Pool Table
- Rain Water Harvesting
- Snooker
- Swimming Pool
- Table Tennis
Bhairaav Group was established in the year 1972 by Chairman Shri. Madan Jain. After a successful stint in the garment industry, the Group forayed into Real Estate at the turn of the 21 st century. Today the Group is counted amongst one of the most promising real estate developers in Mumbai and Navi Mumbai. Since its inception the company has grown from strength to strength and flourished over the years through sheer hard work, dedication and commitment to quality.
Highlights
- Power Back-up
- Visitor Parking
- Maintenance Staff
- Water Supply / Storage
- Rain Water Harvesting
- Lifts
- Security Guards
- Fire Alarm
- Intercom Facility
- Reserved Parking
- Independent Garage
- Servant Quarter
- Swimming Pool
- Park
- Fitness Centre / GYM
- Club / Community Center
- Cafeteria / Food Court
- Club / Community Center
- Adjacent to Main Road
- Park/Green Belt Facing
- Water Connection
- Electric Connection
- Close to Hospital
- Close to School
- Close to Shopping Center/Mall
Configurations
| Type | Area | Possession | Price * |
|---|---|---|---|
| 1BHK Apartment | 693 SqFeet | Within 6 Months | ₹ 92 lakhs |
| 2BHK Apartment | 1,386 SqFeet | Within 6 Months | ₹ 1.46 crore |
RERA
P51700010579 Goldcrest Residency - Phase 2 Active 97% built
Confirmed with MahaRERA on 22 Sep 2026. Registered as "Goldcrest Residency - Phase 2".
- Promoter
- SAVITA HOMEMAKERS LLP
- Registered on
- 31 Aug 2017
- Proposed completion
- Mar 2027 (originally Jun 2021)
- Project type
- Residential / Group Housing
- Planning authority
- Others
- Address as filed
- NEW PALM BEACH ROAD, GHANSOLI, Navi Mumbai (M Corp.), Thane, Thane, 400701
- Land area
- 7,025 sq m (75,618 sq ft)
- Sanctioned built-up area
- 11,138 sq m (119,891 sq ft)
- Buildings
- Harmony - Wing B (30 floors) - 0 of 91 available; Peace - Wing C (30 floors) - 0 of 134 available; Pride - Wing A (30 floors) - 0 of 91 available
- Parking
- Open Space 1, Closed/Covered 306
- Complaints on the portal
- 92
| Building | Unit type | Carpet area | Units |
|---|---|---|---|
| Harmony - Wing B | 1 BHK | 26 sq m (277 sq ft) | 43 |
| Harmony - Wing B | 2 BHK Type 1 | 41 sq m (445 sq ft) | 10 |
| Harmony - Wing B | 2 BHK type 2 | 42 sq m (452 sq ft) | 38 |
| Peace - Wing C | 2 BHK Type 1 | 44 sq m (473 sq ft) | 10 |
| Peace - Wing C | 1 BHK Type 1 | 22 sq m (233 sq ft) | 10 |
| Peace - Wing C | 2 BHK Type 2 | 45 sq m (482 sq ft) | 38 |
| Peace - Wing C | 1 BHK Type 2 | 24 sq m (257 sq ft) | 76 |
| Pride - Wing A | 2BHK TYPE 1 | 41 sq m (445 sq ft) | 10 |
| Pride - Wing A | 1BHK | 26 sq m (277 sq ft) | 43 |
| Pride - Wing A | 2BHK TYPE 2 | 42 sq m (452 sq ft) | 38 |
| Quarterly return | Filed | Built | Units booked |
|---|---|---|---|
| Q2 FY 2024-2025 | not filed - in default | - | - |
| Q3 FY 2024-2025 | not filed - in default | - | - |
| Q4 FY 2024-2025 | 30 Jun 2025 | - | - |
| Q1 FY 2025-2026 | 18 Apr 2026 | - | - |
| Q2 FY 2025-2026 | 18 Apr 2026 | - | - |
| Q3 FY 2025-2026 | 20 Apr 2026 | - | - |
| Q4 FY 2025-2026 | 11 May 2026 | - | - |
| Q1 FY 2026-2027 | not filed - in default | - | - |
Construction progress as reported to the portal
Harmony - Wing B
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 100%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 96%
- Sanitary Fittings within the flats / premises: 96%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 95%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 95%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 94%
Peace - Wing C
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 100%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 97%
- Sanitary Fittings within the flats / premises: 81%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 96%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 91%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 92%
Pride - Wing A
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 100%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 97%
- Sanitary Fittings within the flats / premises: 95%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 96%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 96%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 93%
Common areas and facilities
- Internal Roads & Footpaths: 96% - NA
- Water Supply: 88% - Permanent Muncipal water connection in place
- Sewerage (Chamber, Lines, Septic Tank , STP): 100% - Completed
- Storm Water Drains: 100% - Completed
- Landscaping & Tree Planting: 85% - In later scope of work
- Street Lighting: 93% - Compound wall and perifery lighting done
- Solid Waste Management And Disposal: 97% - NA
- Water conservation /Rain water harvesting: 90% - IN PROGRESS
- Energy managemcnt: 90% - In later scope of work
- Fire protection and fire safety requirements: 91% - In later scope of work
- Electrical meter room, sub-station, receiving station: 93% - In later scope of work
- Aggregate area of recreational Open Space: 0% - NA
- Open Parking: 0% - NA
Reviews
Write a review
Be the first to write a review of Bhairaav Goldcrest Residency Phase 2 and become a Project expert!
- Post an informative review and get 1 additional basic property listing FREE of cost*.
- Your review will be displayed prominently on your property listing page and other pages on the website.
- For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of Bhairaav Goldcrest Residency Phase 2
Enter some positive aspects of Bhairaav Goldcrest Residency Phase 2
Cons:
Enter some negative aspects of Bhairaav Goldcrest Residency Phase 2
Enter some negative aspects of Bhairaav Goldcrest Residency Phase 2
Location
Bhairaav Goldcrest Residency Phase 2, Ghansoli Sector-11, Navi Mumbai - 400701 (Maharashtra)
Nearby
-
Transport
- Ghansoli (~2 km)
- Koparkhairane NMMT Bus Station (~3 km)
- Hindustan Petroleum (~3 km)
- Ghatkopar L1 (~14 km)
- Chhatrapati Shivaji Maharaj International Airport (~19 km)
- Navi Mumbai International Airport (~22 km)
-
Shopping & Dining
- Pizza Hut (<1 km)
- Casino Cafe | Cafe in Ghansoli Navi Mumbai (<1 km)
- DMart (<1 km)
- Satra Plaza (~6 km)
- APMC Grain Market (~6 km)
- bhakti (~12 km)
-
Healthcare
- Majisa Medico (<1 km)
- New Life Medical (~2 km)
- Dr. Dive S Eye Clinic (~2 km)
- Reliance Hospital (~3 km)
- apple hospital (~4 km)
- Spandan Healthcare center (~4 km)
-
Education
- Shrimati Indira Gandhi College of Engineering (<1 km)
- Terna Orchids International Schoool (~2 km)
- North Point School (~3 km)
- Dhirubhai Ambani Knowledge City (~3 km)
- Cht.Sahu Maharaj Vachnalaya (~7 km)
- Indian Institute of Technology Bombay (~13 km)
-
Leisure & Entertainment
- Central Park (~2 km)
- Navi Mumbai Sports Association (~7 km)
- Dadoji Konddev Stadium (~12 km)
- Kharghar Valley Golf Course (~14 km)
- Inox (~14 km)
- Butterfly Park (~15 km)
-
Services
- Axis Bank (<1 km)
- HDFC Bank ATM (<1 km)
- Koparkhairne Fire Station (~2 km)
- MIDC Mahape (~3 km)
- KK POLICE STATION (~3 km)
- India Post (~6 km)
-
Religious Places
- Gurudwara Guru Singh Sabha, koperKhairane (~3 km)
- Koparkhairane Jama Masjid (~3 km)
- Mahalaxmi Mandir KK (~4 km)
- ganesh mandir (~4 km)
- SHRI DATTA GURU MANDIR (~4 km)
- kanchan dharmashala (~4 km)
-
Business & Hospitality
- Country Inn Hotel & Suites (~3 km)
- Reliance Corporate Park (~3 km)
- Millennium Business Park, Mahape Village (~4 km)
- SIEMENS (~5 km)
- Navi Mumbai Marriott Hotel (~9 km)
- CEAT Tyre (~9 km)
- Project ID
- J514211898
- Updated
- Searches
- 1895
- Views
- 1247