Avenue Hills - Kharghar Sector-12, Navi Mumbai
- Builder
- Avenue Lifespaces
- Construction
- Under Construction
- Completion
- Apr, 2028
- Properties
- Apartments
- RERA
- P52000046723
Description
Stunning hill-facing residences with four-level covered car parking
Avenue Hills is a premium residential development project located in Kharghar Sector-12, Navi Mumbai. The project offers spacious 2 and 3 BHK apartments ranging from 604 to 1050 sq. ft., spanning approximately 0.71 acres of land. It offers 1/2 iconic towers of G + 24/29 Storeys, a well-planned residential tower, modern infrastructure, lifestyle-focused facilities, landscaped spaces, recreational amenities, secure community living, efficient layouts, ample ventilation, stylish interiors, modern family lifestyles and 126 units.
Amenities:
- Swimming Pool
- Fully Equipped Gymnasium
- Modern Clubhouse
- Children’s Play Area
- Indoor Games Room
- Jogging / Walking Track
- Senior Citizen Seating Area
- Multipurpose Hall
- CCTV Surveillance
- 24x7 Security
- Intercom Facility
- High-Speed Elevators
- Power Backup
- Fire Fighting System
- Rainwater Harvesting
- Sewage Treatment Plant
- Closed Car Parking
- Internal Roads & Footpaths
- Water Conservation System
- Storm Water Drainage
- Large Green Open Spaces
Avenue Life Spaces is an emerging real estate developer focused on creating modern residential and commercial spaces with quality construction, thoughtful planning, and customer-centric design. The developer aims to deliver contemporary lifestyle projects that combine comfort and convenience. Avenue Life Spaces is committed to developing well-connected communities with landscaped surroundings, lifestyle amenities, and sustainable living concepts.
Highlights
- Swimming Pool
- Fully Equipped Gymnasium
- Modern Clubhouse
- Children’s Play Area
- Indoor Games Room
- Jogging / Walking Track
- Senior Citizen Seating Area
- Multipurpose Hall
- CCTV Surveillance
- 24x7 Security
- Intercom Facility
- High-Speed Elevators
- Power Backup
- Fire Fighting System
- Rainwater Harvesting
- Sewage Treatment Plant
- Closed Car Parking
- Internal Roads & Footpaths
- Water Conservation System
- Storm Water Drainage
- Large Green Open Spaces
Configurations
| Type | Area | Possession | Price * |
|---|---|---|---|
| 2BHK Apartment | 750 SqFeet | Within 2 Years | ₹ 1.6 crore |
| 3BHK Apartment | 1,050 SqFeet | Within 2 Years | ₹ 2.5 crores |
RERA
P52000046723 Avenue Hills Active 98% built
Confirmed with MahaRERA on 22 Sep 2026. Registered as "Avenue Hills".
- Promoter
- Avenue Lifespaces
- Registered on
- 1 Sep 2022
- Proposed completion
- Apr 2028 (originally Dec 2027)
- Project type
- Others
- Planning authority
- Others
- Address as filed
- Plot No-F-92+F-97, Sector-12, Kharghar, Panvel, Raigarh, 410210
- Land area
- 2,889 sq m (31,094 sq ft)
- Sanctioned built-up area
- 13,785 sq m (148,381 sq ft)
- Buildings
- Building Number 1 Residential (29 floors) - 26 of 122 available; Building Number 2 Commercial (3 floors) - 4 of 4 available
- Parking
- Open Space 54, Closed/Covered 124
| Building | Unit type | Carpet area | Units |
|---|---|---|---|
| Building Number 1 Residential | 2BHK | 64 sq m (690 sq ft) | 12 |
| Building Number 1 Residential | 2BHK | 66 sq m (710 sq ft) | 20 |
| Building Number 1 Residential | 2BHK | 61 sq m (662 sq ft) | 32 |
| Building Number 1 Residential | 2BHK | 78 sq m (845 sq ft) | 1 |
| Building Number 1 Residential | 3BHK | 73 sq m (785 sq ft) | 1 |
| Building Number 1 Residential | 2BHK | 62 sq m (664 sq ft) | 2 |
| Building Number 1 Residential | 3BHK | 88 sq m (945 sq ft) | 20 |
| Building Number 1 Residential | 2BHK | 57 sq m (609 sq ft) | 8 |
| Building Number 1 Residential | 2BHK | 61 sq m (659 sq ft) | 6 |
| Building Number 1 Residential | 3BHK | 90 sq m (964 sq ft) | 20 |
| Building Number 2 Commercial | Shop | 287 sq m (3,084 sq ft) | 1 |
| Building Number 2 Commercial | Shop | 243 sq m (2,613 sq ft) | 1 |
| Building Number 2 Commercial | Office space | 47 sq m (501 sq ft) | 1 |
| Building Number 2 Commercial | Office space | 44 sq m (471 sq ft) | 1 |
| Quarterly return | Filed | Built | Units booked |
|---|---|---|---|
| Q2 FY 2024-2025 | not filed - in default | - | - |
| Q3 FY 2024-2025 | not filed - in default | - | - |
| Q4 FY 2024-2025 | 21 May 2025 | - | - |
| Q1 FY 2025-2026 | 28 Jul 2025 | - | - |
| Q2 FY 2025-2026 | 4 Nov 2025 | - | - |
| Q3 FY 2025-2026 | 24 Jan 2026 | - | - |
| Q4 FY 2025-2026 | 20 May 2026 | - | - |
| Q1 FY 2026-2027 | 28 Aug 2026 | - | - |
Construction progress as reported to the portal
Building Number 1 Residential
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 100%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
- Sanitary Fittings within the flats / premises: 95%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 95%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 90%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 70%
Building Number 2 Commercial
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 100%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
- Sanitary Fittings within the flats / premises: 100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%
Common areas and facilities
- Internal Roads & Footpaths: 65% - Work in progress
- Water Supply: 90% - Work in progress
- Sewerage (Chamber, Lines, Septic Tank , STP): 85% - Work in progress
- Storm Water Drains: 70% - Work in progress
- Landscaping & Tree Planting: 0% - In later scope of work
- Water conservation /Rain water harvesting: 90% - Work in progress
- Fire protection and fire safety requirements: 70% - Work in progress
- Electrical meter room, sub-station, receiving station: 85% - Work in progress
Reviews
Write a review
Be the first to write a review of Avenue Hills and become a Project expert!
- Post an informative review and get 1 additional basic property listing FREE of cost*.
- Your review will be displayed prominently on your property listing page and other pages on the website.
- For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of Avenue Hills
Enter some positive aspects of Avenue Hills
Cons:
Enter some negative aspects of Avenue Hills
Enter some negative aspects of Avenue Hills
Location
Avenue Hills, Kharghar Sector-12, Navi Mumbai - 410210 (Maharashtra)
Nearby
-
Transport
- HP (<1 km)
- Khargar Village (<1 km)
- Kharghar (~3 km)
- Belapur Bus Depot (~6 km)
- Navi Mumbai International Airport (~8 km)
- Chhatrapati Shivaji Maharaj International Airport (~31 km)
-
Shopping & Dining
- Cheelizza (<1 km)
- DMart (<1 km)
- Kitchen Wold (~1 km)
- Chaayos Cafe at Kharghar (~2 km)
- Glomax Mall (~2 km)
- APMC Fruit & Vegetable Market (~10 km)
-
Healthcare
- Medicover Hospital (~1 km)
- Advanced Arthritis and Rheumatology Center (~1 km)
- Zeelab Pharmacy (~1 km)
- Medicity Hospital (~1 km)
- Apollo Pharmacy (~1 km)
- Spandan Hospital (~2 km)
-
Education
- Tilak Institute of Pharmacutical Research- Kharghar (<1 km)
- Ryan International School - Kharghar (<1 km)
- Vibgyor High School (~1 km)
- Saraswati College of Engineering, Kharghar (~2 km)
- Society for Applied Microwave Electronics Engineering & Research - Mumbai (~4 km)
- Cht.Sahu Maharaj Vachnalaya (~12 km)
-
Leisure & Entertainment
- Maxus Cinema Hall (<1 km)
- Vasudev Balwant Phadke Park (<1 km)
- Kharghar Valley Golf Course (~3 km)
- Butterfly Park (~5 km)
- Dr. DY Patil Sports Stadium (~7 km)
- Dr. DY Patil Sports Complex (~7 km)
-
Services
- Panvel Muni Corp. Ward A Office (Kharghar Gram Panchayat) (<1 km)
- Navi Mumbai - Kharghar Branch ATM (<1 km)
- Bank of Baroda (<1 km)
- Kharghar Police Station (~1 km)
- Kharghar Post Office (~2 km)
- Tawa Delight (~4 km)
-
Religious Places
- Shiv Mandir (<1 km)
- ISKON (~2 km)
- ISCKON Temple (~2 km)
- ISCKON (~2 km)
- St. Mary's Malankara Catholic Church (~2 km)
- Kharghar Gurdwara (~3 km)
-
Business & Hospitality
- Aditya Birla Science and Technology Company (~5 km)
- Courtyard by Marriott Navi Mumbai (~7 km)
- Central Warehousing Corporation - Kalamboli (~7 km)
- Navi Mumbai Marriott Hotel (~9 km)
- Millennium Business Park, Mahape Village (~13 km)
- Reliance Corporate Park (~16 km)
- Project ID
- J919265231
- Updated
- Searches
- 262
- Views
- 259