Arihant Anmol - Badlapur East, Thane
- Builder
- Arihant Superstructures Ltd.
- Construction
- Completed
- Completion
- Mar, 2022
- Properties
- Apartments
- RERA
- P51700003112
Description
Sprawling residential apartments
Arihant Anmol by s a project by Arihant Superstructures Ltd. at Badlapur east Thane offers 1 bhk and 2 bhk apartment in the size ranges in between 655 to 972 sqt. It has 423 units with 17 buildings in this project. The project host amenities like Gymnasium, clubhouse, indoor games etc. The project is well connected with other parts of city and has all the basic amenities are nearby.
Amenities :
- Gymnasium
- Swimming pool
- Clubhouse
- Jogging Track
- Children’s Play Area
- Indoor Games
- Security Personal
- Power Backup
- Car Parking
- Rainwater Harvesting
- Sewage Treatment
Arihant Superstructures Ltd . is a leading player in Navi Mumbai real estate industry. Everyone dreams to have their own home & they help many of them to make their dreams come true. They build each home painstakingly, with focus on Quality, Useful detailing & ensure Value for money. They desire to earn people's trust and confidence while they create whenever they launch their new product and services.
Highlights
- Power Back-up
- Maintenance Staff
- Water Supply / Storage
- Rain Water Harvesting
- Lifts
- High Speed Internet
- Security Guards
- Electronic Security
- Intercom Facility
- Balcony
- Reserved Parking
- Park Facing
- Swimming Pool
- Park
- Fitness Centre / GYM
- Club / Community Center
Configurations
| Type | Area | Possession | Price * |
|---|---|---|---|
| 1BHK Apartment | 613 SqFeet | Immediate/Ready to move | ₹ 25 lakhs |
| 1BHK Apartment | 700 SqFeet | Immediate/Ready to move | ₹ 25.7 lakhs |
| 2BHK Apartment | 915 SqFeet | Immediate/Ready to move | ₹ 36.26 lakhs |
| 2BHK Apartment | 956 SqFeet | Immediate/Ready to move | ₹ 37.75 lakhs |
RERA
P51700003112 ARIHANT ANMOL PHASE II Completed
Confirmed with MahaRERA on 21 Sep 2026. Registered as "ARIHANT ANMOL PHASE II".
- Promoter
- ARIHANT VATIKA REALTY PRIVATE LIMITED
- Registered on
- 4 Aug 2017
- Proposed completion
- Mar 2022 (originally Sep 2020)
- Project type
- Residential / Group Housing
- Planning authority
- Others
- Address as filed
- Badlapur, Badlapur, Badlapur (M Cl), Ambarnath, Thane, 421503
- Land area
- 4,224 sq m (45,466 sq ft)
- Sanctioned built-up area
- 10,390 sq m (111,839 sq ft)
- Buildings
- B1 (13 floors); B2 (13 floors); B3 (12 floors)
- Parking
- Open Space 0, Closed/Covered 85
- Complaints on the portal
- 4
| Building | Unit type | Carpet area | Units |
|---|---|---|---|
| B2 | SHOP NO. 9 AND 15 | 18 sq m (194 sq ft) | 2 |
| B2 | SHOP NO. 10 AND 11 | 19 sq m (201 sq ft) | 2 |
| B2 | SHOP NO. 12 | 16 sq m (173 sq ft) | 1 |
| B2 | SHOP NO. 13 | 15 sq m (161 sq ft) | 1 |
| B2 | 2 BHK | 41 sq m (438 sq ft) | 48 |
| B2 | SHOP NO. 14 | 19 sq m (203 sq ft) | 1 |
| B2 | SHOP NO. 16 | 10 sq m (102 sq ft) | 1 |
| B2 | SHOP NO. 8 | 10 sq m (102 sq ft) | 1 |
| B2 | 1 BHK | 29 sq m (316 sq ft) | 23 |
| B3 | SHOP NO. 7 | 13 sq m (136 sq ft) | 1 |
| B3 | 1 BHK | 29 sq m (309 sq ft) | 36 |
| B3 | SHOP NO. 3 AND 4 | 18 sq m (194 sq ft) | 2 |
| B3 | SHOP NO. 1 AND 6 | 10 sq m (102 sq ft) | 2 |
| B3 | SHOP NO. 2 AND 5 | 19 sq m (200 sq ft) | 2 |
| B3 | 2 BHK | 41 sq m (438 sq ft) | 36 |
Construction progress as reported to the portal
B1
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 0%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
- Sanitary Fittings within the flats / premises: 100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%
B2
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 0%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
- Sanitary Fittings within the flats / premises: 100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%
B3
- Excavation: 100%
- Basement (if any): 100%
- Podiums (if any): 0%
- Plinth: 100%
- Stilt Floor: 100%
- Slabs of Super Structure: 100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises: 100%
- Sanitary Fittings within the flats / premises: 100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks: 100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.: 100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.: 100%
Common areas and facilities
- Internal Roads & Footpaths: 0% - CC WITH TREMIX
- Water Supply: 95% - WATER LINE
- Sewerage (Chamber, Lines, Septic Tank , STP): 100% - WIP
- Storm Water Drains: 100% - WIP
- Landscaping & Tree Planting: 80% - COMPLETED
- Street Lighting: 0% - WIP
- Community Buildings: 100% - COMPLETED DURING CONSTRUCTION OF PHASE I
- Treatment And Disposal Of Sewage And Sullage Water: 100% - WIP
- Solid Waste Management And Disposal: 0% - WIP
- Water conservation /Rain water harvesting: 50% - WIP
- Fire protection and fire safety requirements: 95% - WIP
- Electrical meter room, sub-station, receiving station: 80% - WIP
- Aggregate area of recreational Open Space: 80% - WIP
Reviews
Write a review
Be the first to write a review of Arihant Anmol and become a Project expert!
- Post an informative review and get 1 additional basic property listing FREE of cost*.
- Your review will be displayed prominently on your property listing page and other pages on the website.
- For Brokers & Builders: Your review will be displayed on your profile and your profile will get more visibility from all the pages your review appears on.
Please try to write your review from a neutral point of view.
Pros:
Enter some positive aspects of Arihant Anmol
Enter some positive aspects of Arihant Anmol
Cons:
Enter some negative aspects of Arihant Anmol
Enter some negative aspects of Arihant Anmol
Location
Arihant Anmol, Badlapur East, Thane - 421102 (Maharashtra)
Nearby
-
Transport
- Nayara Petrol Pump (~3 km)
- Badlapur (~3 km)
- Kulgaon Bus Station (~4 km)
- Ambarnath (~13 km)
- Navi Mumbai International Airport (~36 km)
- Chhatrapati Shivaji Maharaj International Airport (~56 km)
-
Shopping & Dining
- mrunal family restaurant (<1 km)
- Ratnakokan (<1 km)
- Cafe Dlite (~3 km)
- Wake Up Cafe (~3 km)
- Kohinoor Market (~4 km)
- Thursday Market (~5 km)
-
Healthcare
- Zeelab Pharmacy (~3 km)
- Urmi Eye Clinic and Phaco Centre (~3 km)
- Seven Palms Hospital (~3 km)
- Apollo Pharmacy (~4 km)
- Rural Hospital (~7 km)
- Shobha Hospital (~13 km)
-
Education
- ZP School (~3 km)
- Adarsh Vidya Mandir (~3 km)
- Grantha sakha. (~3 km)
- A (~4 km)
- Saraswati College of Engineering, Kharghar (~32 km)
- Bharati Vidyapeeth (~35 km)
-
Leisure & Entertainment
- main theatre (~3 km)
- Vaishali Talkies (~4 km)
- Nana Nani Park (~4 km)
- Malanggad (~11 km)
- KDMC sports complex (~23 km)
- Kharghar Valley Golf Course (~30 km)
-
Services
- Kulgaon Police Station (~2 km)
- State Bank of India (~2 km)
- HDFC Bank ATM (~3 km)
- Kulgaon Postoffice (~3 km)
- Ambarnath Taluka Court (~9 km)
- Ambernath Municipal Corporation (~13 km)
-
Religious Places
- Jamma Masjid (~3 km)
- GANESH TEMPLE (~3 km)
- Rameshwadi Church (~3 km)
- mandir (~4 km)
- Saibaba Mandir (~4 km)
- Datta Mandir (~4 km)
-
Business & Hospitality
- Badlapur MIDC (~1 km)
- Additional Industrial Area (~10 km)
- Maharashtra Industrial Development Centre - MIDC Taloja (~20 km)
- Millennium Business Park, Mahape Village (~34 km)
- Reliance Corporate Park (~34 km)
- Marriott Executive Apartments Navi Mumbai (~34 km)
- Project ID
- J791190097
- Updated
- Searches
- 5446
- Views
- 2198